20020208 TZHC Dar es Salaam

20020208 TZHC Dar es Salaam

The plaintiff is not entitled to interest as the amount was unascertained and the delay was not solely attributable to the defendant; however, the plaintiff is entitled to costs.

Citation
20020208 TZHC Dar es Salaam
Parties
Plaintiff: John Jacob Construction Ltd; Defendant: Aduco International BV
Court
TZHC
Jurisdiction
Tanzania
Judgment Date
8 February 2002
Procedural Posture
Civil / Judgment After Partial Settlement and Trial on Remaining Issues
Outcome
interest claim dismissed, costs awarded to plaintiff
Legal Topics
Interest on Delayed Payments, Costs of Suit, Settlement Agreements
Source Language
English

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

John Jacob Construction Ltd

Plaintiff

Aduco International BV

Defendant

Procedural Posture

Civil / Judgment After Partial Settlement and Trial on Remaining Issues

  1. 1 Whether the settlement entered on 1/3/2001 between the plaintiff and the defendant was final and conclusive including the claim on interest and costs
  2. 2 If not, what reliefs are the parties entitled to

Ratio Decidendi

The plaintiff is not entitled to interest as the amount was unascertained and the delay was not solely attributable to the defendant; however, the plaintiff is entitled to costs.

Court Disposition

interest claim dismissed, costs awarded to plaintiff

Orders

  • Plaintiff's claim for interest is dismissed
  • Plaintiff is awarded costs