bunda district council vs mispa construction co ltd 2021 tzhccomd 3510 8 december 2021

bunda district council vs mispa construction co ltd 2021 tzhccomd 3510 8 december 2021

Failure to comply with section 35(1)(a) of the Arbitration Act, 2020 and agreed procedure constituted a serious irregularity likely to cause injustice, warranting setting aside the award.

Citation
bunda district council vs mispa construction co ltd 2021 tzhccomd 3510 8 december 2021
Parties
Petitioner: Bunda District Council; Respondent: Mispa Construction Co. Ltd
Court
TZHCCOMD
Jurisdiction
Tanzania
Judgment Date
8 December 2021
Procedural Posture
Miscellaneous Commercial Cause / Ruling on Petition to Set Aside Arbitral Award
Outcome
final award set aside in whole
Legal Topics
Setting Aside Arbitral Award, Natural Justice, Right to Be Heard, Procedural Irregularity
Source Language
English

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 3 Authorities cited 10 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Bunda District Council

Petitioner

Mispa Construction Co. Ltd

Respondent

Procedural Posture

Miscellaneous Commercial Cause / Ruling on Petition to Set Aside Arbitral Award

  1. 1 Whether the arbitral award was improperly procured due to procedural irregularity and denial of right to be heard
  2. 2 Whether the arbitrator awarded specific claims without proof

Ratio Decidendi

Failure to comply with section 35(1)(a) of the Arbitration Act, 2020 and agreed procedure constituted a serious irregularity likely to cause injustice, warranting setting aside the award.

Court Disposition

final award set aside in whole

Orders

  • Final Award by Sole Arbitrator set aside in whole
  • No order as to costs