19860122 TZCA Dodoma

19860122 TZCA Dodoma

Plaintiff was not entitled to further payment on quantum meruit as contract was entire and no new agreement to pay for incomplete works could be inferred; frustration was not established as difficulties were foreseeable and within parties' control; plaintiff not entitled to payment for unused materials as...

Source-derived case information.

Citation
19860122 TZCA Dodoma
Parties
Plaintiff: Mpajazi Building Contractor (sole proprietor: Mr. Gislar Macarius Kihaule); Defendant: Parokia ya Kidachi Katoliki ya Dodoma
Court
TZCA
Jurisdiction
Tanzania
Judgment Date
22 January 1986
Procedural Posture
Civil / Final Judgment
Outcome
Both claim and counterclaim dismissed.
Legal Topics
Rescission of Contract, Quantum Meruit, Building Contracts, Frustration, Overpayment, Valuation of Works
Source Language
en
Contract Law Construction Law Rescission of Contract Quantum Meruit Building Contracts Frustration Overpayment Valuation of Works

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 5 Party arguments 2 Amounts and remedies 7
Sign in to unlock

Parties

Mpajazi Building Contractor (sole proprietor: Mr. Gislar Macarius Kihaule)

Plaintiff

Parokia ya Kidachi Katoliki ya Dodoma

Defendant

Procedural Posture

Civil / Final Judgment

  1. 1 Whether plaintiff's failure to perform was due to frustration or impossibility
  2. 2 Whether amendments to building plans entailed extra work
  3. 3 Whether plaintiff is entitled to further payment on quantum meruit

Ratio Decidendi

Plaintiff was not entitled to further payment on quantum meruit as contract was entire and no new agreement to pay for incomplete works could be inferred; frustration was not established as difficulties were foreseeable and within parties' control; plaintiff not entitled to payment for unused materials as relinquishment was supported by consideration; defendant not entitled to recover alleged overpayment as payments were certified by architect with full authority.

Court Disposition

Both claim and counterclaim dismissed.

Orders

  • Each party to bear its own costs.