njake enterprises ltd vs blue rock ltd another 2018 tzca 304 3 december 2018
The certificate of delay referenced a non-existent letter and was therefore invalid; without a valid certificate, the appeal was filed out of time and is incompetent.
- Citation
- njake enterprises ltd vs blue rock ltd another 2018 tzca 304 3 december 2018
- Parties
- Appellant: Njake Enterprises Limited; 1st Respondent: Blue Rock Limited; 2nd Respondent: Rock and Venture Company Limited
- Court
- TZCA
- Jurisdiction
- Tanzania
- Judgment Date
- 3 December 2018
- Procedural Posture
- Civil Appeal / Preliminary Objection Ruling
- Outcome
- appeal struck out
- Legal Topics
- Time Bar, Certificate of Delay, Appeal Procedure, Preliminary Objection
- Source Language
- English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Full judgment text Downloadable case file Legal principles 3 Authorities cited 8 Party arguments 2 Amounts and remedies 2
Parties
Njake Enterprises Limited
Appellant
Blue Rock Limited
1st Respondent
Rock and Venture Company Limited
2nd Respondent
Procedural Posture
Civil Appeal / Preliminary Objection Ruling
Legal Issues
- 1 Whether the appeal was filed within the prescribed time limit
- 2 Whether the certificate of delay was valid and effective for exclusion of time
- 3 Whether errors in the certificate of delay can be treated as mere technicalities
Ratio Decidendi
The certificate of delay referenced a non-existent letter and was therefore invalid; without a valid certificate, the appeal was filed out of time and is incompetent.
Court Disposition
appeal struck out
Orders
- The appeal is struck out for being time barred.
- The respondents are awarded costs.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment