palm green ltd vs crje estate ltd johari rotana hotel 2022 tzhccomd 247 26 august 2022

palm green ltd vs crje estate ltd johari rotana hotel 2022 tzhccomd 247 26 august 2022

Although the defendant breached the contract by delaying payment, the breach was excused due to the force majeure event of the COVID-19 pandemic, which was widely known and affected both parties. The penalty clause, while contractually agreed, is unenforceable in this context due to the excusing circumstances. No...

Source-derived case information.

Citation
palm green ltd vs crje estate ltd johari rotana hotel 2022 tzhccomd 247 26 august 2022
Parties
Plaintiff: Palm Green Limited; Defendant: CRJE Estate Ltd (Johari Rotana Hotel)
Court
TZHCCOMD
Jurisdiction
Tanzania
Judgment Date
26 August 2022
Procedural Posture
Commercial Case / Judgment
Outcome
Suit dismissed with no order as to costs.
Legal Topics
Breach of Contract, Force Majeure, Penalty Clauses, COVID 19 Pandemic, Damages
Source Language
en
Contract Law Commercial Law Breach of Contract Force Majeure Penalty Clauses COVID 19 Pandemic Damages

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 1 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Palm Green Limited

Plaintiff

CRJE Estate Ltd (Johari Rotana Hotel)

Defendant

Procedural Posture

Commercial Case / Judgment

  1. 1 Whether there is a breach of contract by the defendant in clause 4.5 and 4.6 in contract No.25 and 26 respectively
  2. 2 Whether the penalty interest of 1% per day from delay payment under clause 4.6 of contract No.26 and clause 4.5 of contract No.25 is reasonable and enforceable by the court
  3. 3 Whether the plaintiff is entitled to claim a penalty amount exceeding the principal debt

Ratio Decidendi

Although the defendant breached the contract by delaying payment, the breach was excused due to the force majeure event of the COVID-19 pandemic, which was widely known and affected both parties. The penalty clause, while contractually agreed, is unenforceable in this context due to the excusing circumstances. No penalties are awarded.

Court Disposition

Suit dismissed with no order as to costs.