reni international company ltd vs geita gold mining ltd 2020 tzhccomd 57 26 may 2020

reni international company ltd vs geita gold mining ltd 2020 tzhccomd 57 26 may 2020

The defendant breached the contract by allowing local authorities to interfere with and fundamentally alter the contract's terms, resulting in frustration and constructive termination. The defendant's actions, including issuing a new tender for the same works and failing to issue further LPOs, constituted breach....

Source-derived case information.

Citation
reni international company ltd vs geita gold mining ltd 2020 tzhccomd 57 26 may 2020
Parties
Plaintiff: RENI INTERNATIONAL COMPANY LTD; Defendant: GEITA GOLD MINING LIMITED
Court
TZHCCOMD
Jurisdiction
Tanzania
Judgment Date
26 May 2020
Procedural Posture
Commercial Case / Judgment
Outcome
Judgment for the plaintiff in part
Legal Topics
Breach of Contract, Frustration of Contract, Corporate Social Responsibility, Damages, Variation of Contract
Source Language
en
Contract Law Commercial Law Breach of Contract Frustration of Contract Corporate Social Responsibility Damages Variation of Contract

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 3 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

RENI INTERNATIONAL COMPANY LTD

Plaintiff

GEITA GOLD MINING LIMITED

Defendant

Procedural Posture

Commercial Case / Judgment

  1. 1 Whether the contract was subject to changes and/or variations and under what circumstances
  2. 2 Whether the defendant frustrated or caused to be frustrated the performance of the contract by allowing political interference thus amounting to constructive termination
  3. 3 Whether there was a breach of the contract by either party

Ratio Decidendi

The defendant breached the contract by allowing local authorities to interfere with and fundamentally alter the contract's terms, resulting in frustration and constructive termination. The defendant's actions, including issuing a new tender for the same works and failing to issue further LPOs, constituted breach. However, the plaintiff failed to strictly prove special damages for loss of profit and supplier payments, but was entitled to general damages for breach.

Court Disposition

Judgment for the plaintiff in part

Orders

  • Defendant to pay plaintiff Tshs. 20,000,000 as general damages
  • Defendant to pay interest on the decretal sum at 7% per annum from date of judgment to full payment