shabbirdin and company limited vs tanzania road agency tanroads 2015 tzhccomd 2116 28 september 2015

shabbirdin and company limited vs tanzania road agency tanroads 2015 tzhccomd 2116 28 september 2015

The court found sufficient cause in the parties' joint petition and granted an extension of six months for compliance with its previous order.

Source-derived case information.

Citation
shabbirdin and company limited vs tanzania road agency tanroads 2015 tzhccomd 2116 28 september 2015
Parties
Applicant: Shabbirdin and Company Limited; Respondent: Tanzania Roads Agency (TANROADS)
Court
TZHCCOMD
Jurisdiction
Tanzania
Judgment Date
28 September 2015
Procedural Posture
Miscellaneous Commercial Cause / Ruling on Joint Petition for Extension of Time
Outcome
Extension of time granted
Legal Topics
Extension of Time, Compliance With Arbitral Award
Source Language
en
Arbitration Civil Procedure Extension of Time Compliance With Arbitral Award

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 1 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Shabbirdin and Company Limited

Applicant

Tanzania Roads Agency (TANROADS)

Respondent

Procedural Posture

Miscellaneous Commercial Cause / Ruling on Joint Petition for Extension of Time

  1. 1 Whether the parties should be granted an extension of time to comply with the court's previous order regarding quantification of costs

Ratio Decidendi

The court found sufficient cause in the parties' joint petition and granted an extension of six months for compliance with its previous order.

Court Disposition

Extension of time granted

Orders

  • The parties are granted six (6) more months from the date of this order to comply with the court's order made on 08.10.2014 regarding quantification of costs.