Civil Appeal No

Civil Appeal No

The appellant had not discharged its obligations under the contract by failing to hand over all assets, specifically the open yard, and therefore was not entitled to the balance of the purchase price or specific performance.

Source-derived case information.

Citation
Civil Appeal No
Parties
Appellant: Sisal Kamba Spinning Company Ltd. (Under Receivership); Respondent: TPM (1998) Limited
Court
TANZLII
Jurisdiction
Tanzania
Judgment Date
1 January 1998
Procedural Posture
Civil Appeal / Judgment on Appeal
Outcome
appeal dismissed
Legal Topics
Breach of Contract, Specific Performance, Sale of Land
Source Language
en
Contract Law Breach of Contract Specific Performance Sale of Land

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Sisal Kamba Spinning Company Ltd. (Under Receivership)

Appellant

TPM (1998) Limited

Respondent

Procedural Posture

Civil Appeal / Judgment on Appeal

  1. 1 Whether the parties discharged their respective obligations under the contract
  2. 2 Whether the appellant breached the contract by failing to deliver all assets as per the sale agreement
  3. 3 Whether the appellant was entitled to specific performance or other reliefs

Ratio Decidendi

The appellant had not discharged its obligations under the contract by failing to hand over all assets, specifically the open yard, and therefore was not entitled to the balance of the purchase price or specific performance.

Court Disposition

appeal dismissed

Orders

  • Appeal dismissed with costs