20041027 TZCA Arusha

20041027 TZCA Arusha

The certificate of delay issued by the Registrar was factually incorrect and misleading because the requested documents had not been officially delivered to the appellant, as no court fees had been paid. Strict compliance with Rule 83(1) is required, and the exclusion of time was not justified. Therefore, the appeal...

Source-derived case information.

Citation
20041027 TZCA Arusha
Parties
Appellant: The Board of Trustees of the National Social Security Fund; Respondent: New Kilimanjaro Bazaar Limited
Court
TZCA
Jurisdiction
Tanzania
Judgment Date
27 October 2004
Procedural Posture
Civil Appeal / Ruling on Preliminary Objection
Outcome
preliminary objection upheld; certificate of delay struck out with costs
Legal Topics
Certificate of Delay, Appeal Timelines, Court Fees, Computation of Limitation Period
Source Language
en
Civil Procedure Certificate of Delay Appeal Timelines Court Fees Computation of Limitation Period

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 6 Party arguments 2
Sign in to unlock

Parties

The Board of Trustees of the National Social Security Fund

Appellant

New Kilimanjaro Bazaar Limited

Respondent

Procedural Posture

Civil Appeal / Ruling on Preliminary Objection

  1. 1 Whether the certificate of delay issued by the Registrar was proper and valid for exclusion of time under Rule 83(1) of the Court of Appeal Rules
  2. 2 Whether the appeal was filed within the prescribed time limit

Ratio Decidendi

The certificate of delay issued by the Registrar was factually incorrect and misleading because the requested documents had not been officially delivered to the appellant, as no court fees had been paid. Strict compliance with Rule 83(1) is required, and the exclusion of time was not justified. Therefore, the appeal was not filed within the prescribed time limit.

Court Disposition

preliminary objection upheld; certificate of delay struck out with costs

Orders

  • The certificate of delay dated 14 July 2003 is struck out with costs.