20151120 TZHC Dar es Salaam3
- Citation
- 20151120 TZHC Dar es Salaam3
- Status
- Judgment
- Jurisdiction
- Tanzania
- Court
- TZHC
- Decision
- 20 November 2015
- Posture
- Commercial Case / Final Judgment
- Language
- English
More details
- Court
- TZHC
- Decision
- 20 November 2015
- Posture
- Commercial Case / Final Judgment
- Language
- English
On this page
Professional case brief
Research organized from the available case record
01
Holding and result
Plaintiff failed to prove payment of advance money to the contractor and failed to comply with contractual and procedural requirements for indemnity under the bonds; therefore, the 2nd defendant is not liable to indemnify the plaintiff.
Court disposition
suit against 2nd defendant dismissed with costs
Orders
- suit against 2nd defendant dismissed with costs
02
Material facts
Parties
Twiga Packers Limited
PlaintiffApplied Mechanical Engineering Co. Limited
1st DefendantInsurance Group of Tanzania Limited
2nd DefendantAmounts and remedies
- Advance Payment Bond: TZS 15,586,040
- Performance Bond: TZS 15,586,040
- Claimed as Costs of Bonds: TZS 31,172,080
- Claimed as Special Damages for Loss of Business: USD 52,962.34
03
Procedural history
Posture
Commercial Case / Final Judgment
04
Questions and positions
Legal issues
- 01
Whether the 2nd defendant is bound to indemnify the plaintiff for default of the 1st defendant
- 02
To what reliefs are the parties entitled
Party arguments
- Applicant
- Plaintiff argued that the 2nd defendant issued performance and advance payment bonds as guarantees for the 1st defendant's work, and sought indemnity for default, special damages for loss of business, and costs.
- Respondent
- 2nd defendant argued it was not party to the construction contract, its bonds were contracts of surety not guarantees, plaintiff failed to prove payment or compliance with claim procedures, and any losses were due to plaintiff's own negligence.
05
Court’s reasoning
Legal principles
- 01
Terms of Advance Payment Bond
Payment of advance money to contractor is an express condition of indemnity under the bond.
- 02
Legal principle 2
Employer must comply with contract conditions and claim procedures to be entitled to indemnity under performance bond.
06
Ratio, limits and disposition
Ratio decidendi
Plaintiff failed to prove payment of advance money to the contractor and failed to comply with contractual and procedural requirements for indemnity under the bonds; therefore, the 2nd defendant is not liable to indemnify the plaintiff.
Obiter and limits
- Losses from lease agreement are attributable to plaintiff's own failure to take contractual precautions for building under construction.
- Tenant's acceptance of premises under construction may waive claims for defects or delays.
Court disposition
suit against 2nd defendant dismissed with costs
- suit against 2nd defendant dismissed with costs
Source and reliance status
TZHC · 20 November 2015
This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.
Judgment reading view
Judgment text
The complete available source text.
TZHC
Judgment· 20 November 2015
~ :r-:.1··~"", ' .,,.: ·. ~~.,.,.,,.,___ t.,.;;i;~'; •• ,._,_.:,.-...~·-·.•'·•- '- ••• I ; ~ -·1,;1:,.), 11 . ·~, ,J/·\i,~ . IN THE HIGH COlJR.T OF TitNZ..~N"IA (COMMERCIAL DIVISION) ,.
AT DAR ES SALAAM .,. COMMERCIAL CASE NO. 13 OF 2014 TWIGA PACKERS LIMITED ................................... PLAINTIFF
VERSUS
APPLIED MECHANICAL ENGINEERING CO. LIMITED ............: ................... :.............. l 8T DEFENDANT
INSURANCE GROUP OF TANZANIA LIMITED ................................... 2ND DEFENDANT
JUDGMENT Mansoor, J: Date of JUDGMENT- 20TH NOVEMBER 2015 Twiga Packers Limited, the plaintiff' filed a suit against Applied . Mechanical Engineering Co. Limited "the 1st defendant" and • •• Insurance Group of Tanzania Limited, .. "the 2 nd defendant" for payments of THz 31,172,000.00 being costs of bonds, payment 1 . of USD 52,962.34 as· special damages for loss of business, general damages, interests and costs of the suit. In the plaint, the plaintiff alleges that on 18 th December 2012, the plaintiff and the 1st defendant entered into a construction agreement for construction of lift ext~nsion in the DRTC Building and installation of New Panoramic Elevator on Plot No. 191 Nyerere Road, Dar es Salaam for a sum of THz f 155,860,400. The plaintiff alleges further that, the 2 nd defendant issued a guarantee for the performance of the work by the 1st defendant. The 2 nd defendant provided an Advance Payment Bond of THz 15,586,040.99 and Perfonpance Bond of THz 15,586,040. The plaintiff alleges that th~ 1s.t defendant received advanced pay~ents of THz 15,586,040 from the plaintiff, but the 1st Defendant did not show up to accomplish the Work. 2 The,.: plaintiff aileges further that the agreed '-' time frai-n.e for completion of the Work was 20 weeks, and relying on that the plaintiff entered into a lease agreement with Swiss Port Training ""Centre for two years for two floors of
the area measuring 556 square meters at the monthly rent of USD 52,962.34. Swiss Port Training Centre had to terminate the contract as the Elevator was not done and occupied only 278 square meters instead of 556 square meters excluding the top floor for there was no lifts/ elevators. Further, the plaintiff alleges that the plaintiff reputation was tarnished as the other tenants vacated the building. The 2 nd defendant issued a discharge voucher of THz 15,000,000 as full and final settlement of the plaintiffs claims under the Bonds, the plaintiff refused to take the amount offered by the 2 nd defendant, hence the plaintiffs suit against the defendants. 'The 1st defendant did not appear in Court, and it did not file - any defence, hence a Default Judgement was. enter~d against 3 it on 25 th .June · 2015. under Rule 22 (1) of the 'High , Ccn~rt (Commercial Division) Procedure Rules, 2012, for all the prayers contained in For~ No. 1 except the -prayer for general ..., damages. As for the 2 nd defendant, the insurance company, they filed their written statement of defence saying that it was not a party to the Construction°" Contract betweei;i the plaintiff and the 1 st defendant and it was not bound by its terms, and that it had no obligations to execute works relating to the lift extension in the DRTC Building. While the 2 nd defendant admits to ·have issued the Advance Payment
Bond and the Performance Bond, it denies that those were not guarantees to . the effect that the 1st defendant will finish the contractual works within 20 weeks, and that the Bonds are pot the guarantees to either the plaintiff or the 1st defendant but admits that the Bonds are contracts of surety, whereby the 2 nd defendant stands as surety ·of the 1 st defendant for the sum not exceeding THz 15,586,040 in the Advance Payment Bond and fdr the: sum not. exceeding THz 15,586,040 in the - 4 Performai.7.ce Bond, and. that the ainount of. surety must always ·conform to the specific reliefs stated in the Bonds . ..., It was the defence taken by the 2 nd defendant that the plaintiff did not take necessary steps to show and prove that there was a valid claim under any of the Bonds in a manner that would have entitled the plaintiff to any relief. That there were no particulars of proof of advanced payment by the plaintiff to the 1st defendant, there was no proof of discharge of° the employers obligations, or a notice of claim, or termination that was served on the Contractors and the Surety, and that there were no particulars of actual loss suffered under the Contract, or . the defects that have occurred to the Works under· the Contra.et which. would have constituted a claim under the Bonds. That the Plaintiff was offered some payments but have refused to accept those payme~ts that
v\rould have been payable to the plaintiff under the Advance Payment Bond, subject to proof that the · plain~ff had paid the Advance payment to the 1st defendant, ·and that having said in the ' · plaint that the Contractor-·performed no work at: all under" the 5 Corttract; the Plaintiff is not ·entitled to present:a.i.7:y claim vvith respect to the money payable under the Performance Bond, and that the entire claim is premature and unacceptable for want of proper""claim procedures. The 2 nd defendant stated in its defence that the plaintiff being an employer was negligent and contributed to its own loss as it was negligent and reckless in that it entered into a Contract with the Contractor without taking steps to ensure that the Contractor is trustworthy, duly qualified, registered and experienced for the Class of the Contracted Works, and that the plaintiff entered into a lease agreement on a building known to them to being under construction without taking . any precautions or making any provisions for circumstances that would warrant extension of time to complete the works. The 2 nd plaintiff therefore prayed for dismissal of the suit against it. 6 - . ' ,.._-;-:__..:....:,;....: '";:.-::. ... · .. -~ .----., ::..~~.;..~·~ ~· ·. '-~-- During·· the · Final Trial . Conferenc~) • the. -.. '.-Court . ~ ' ., in . consultations with the Counsel for the Parties recorded
the fallowing issues; 1. Whether the 1 st defendant breached the Agreement; 2. Whether the 2 nd defendant is bound to indemnify the plaintiff for default of the 1st defendant; 3. To what reliefs are the parties' entitled. It should be noted that issue number one need not be determined as there was a Default Judgement already en~ered by the Court as against the 1st Defendant, thus the issues remairied for determination were the 2 nd and 3 rd issues.
1. Whether the 2 nd defendant is duty bound to indemnify the plaintiff for the default of the 1st defendant: The plaintiff brought only one witne_ss one Mary Musira, she presented t9 court the. following exhibits: 7 1.·Exh Pl- The Agreement between the plaintiff and the 1st defendant for Construction of the Elevators; . .
2. Exh P2- Performance Bond executed by the 2 nd Defendant; 3. Exh P3- Advanced Payment Bond executed by the Defendant; 4. Exh P4 - Handover Agreement between Twiga Packers Limited and Swissport Tanzania Limited; 5. Exh PS- correspondences between Swissport Tanzania Limited and Twiga Packers Limited; Tb.is witness admitted during cross examination that she did not attach any receipt or voucher showing that Twiga Packers have paid the Advance Payment payments to the 1st defendant, and admitted that the Rules under the Advance Payment Bond is to pay the Contractor. She· also testified during cross ~x~ination that at the time the 8 .. plaintiff entered into 3..t.7. agreement ·with Swissport, the lift was not yet installed. The 2 nd defendant admitted to have issued the two bonds that is the 1st Advance Payment Bond was issued on 25 th February 2013 for. the period of 18th February 2013 to 17 th February 2014, covering the amount not exceeding THz 15,586,040, and the 2 nd Bond was the Performance Bond issued on 18 th February 2013 for an amount not exceeding THz 15,586,040. As admitted by PW 1 that she did not p·rove before the Court that the Plaintiff had actually paid the 1st . Defendant, .the Contractor, the Advance payments, the plaintiff cannot be heard to claim for refund of the Advance payment which PWl had admitted not to be able to prove before the Court that the plaintiff
had paid this . money-to the_ Contractor. I agree with the submissi9ns by the Counsel for the 2 nd defendant that payment of this money to the Contractor IS · an express "condition of 9 ... _. indemri'ity under ·the· B·ond. The.. 'piaintiff. alleged ·that it paid the Advance Money to the Contractor in paragraph 8 of the Plaint and also paragraph 9 and 11 of (PW)) Mary Musira's statement in lieu of evidence in chief, but when cross examined, this witness of the plaintiff admitted that she did not bring any proof before the Court; a receipt or voucher proving that the plaintiff had actually paid this money to the Contractor. Thus failure to prove the Payment of the Advanced Payment to the 1st Defendant, wI:ich is the. basis of the·· Claims against the 2 nd defendant 1s fatal and extinguishes the plaintiffs claims against · the 2 nd defendant.~ On the performance Bond, the plaintiff would have been entitled to payment of the indemnity by the Surety, if it had declared the Contractor to be in default of the performance of the Contract, and that as_ the Employer it . has. performed the Employers Obligations under the ·•· Contract..; J'he Employer, the plaintiff h_ereip. has faile_d to prove by evidence that it complied vvith the conditions set in the Terms and Condition Clauses of the Contract .., between the plaintiff and the 1st defendant. Even when it were to be found that the
plaintiff is entitled to indemnity by the Surety, the plaintiff failed to prove before the Court that it followed the procedures for payment of surety, this was clearly explained by one Yvette Deogratius, the Claims Officer of the 2 nd Defendant, who admitted during cross examination that she had received the Claims Forms and copies of Bonds from the Plaintiff. She also admitted that the 2 nd defendant issued the discharge voucher to the plaintiff, but the voucher was vvritten without prejudice, meaning that the document was not conclusive, and ·the plaintiff was required to fulfil some conditions to entitle them to payments of indemnity. The plaintiff never submitted to the Surety a Notice or a Declaration that the Works - Bond was 'issued was not under which the Performance ' ' 11 performed. The Declaration is required to be certified by the Registered Engineer from the Con tractors Registration Board, there was no such Declaration presented to the Surety. Thus the Claimant/the plaintiff had failed to prove its clams to entitle it _to payments. In answer to the issue, I would therefore say that the Surety, i.e. 2 nd Defendant would have been liable to pay or indemnify the plaintiff herein, if the plaintiff would have been able to prove its case on the required standards. The plaintiff failed to prove before the C~urt that it_ actually made the payments to· . . . the 1st
defendant to entitle it to recover from the Advanced Payment Bond, and also it failed to prove that it has complied with the conditions set in the Contract between_ the employer and the Contractor to entitle it to payment under the 2 nd Performance Bond, also it has failed to prove that it has followed the procedure in presenting its claims for indemnity before the 2 nd defendant .2. To what remedies are the parties entit1e·d. 12 ... The prayer of payments of THz 31,J72,080 as costs ·of the Bonds, this cannot be recovered from the 2 nd defendant, for the reasons given herein above. As for the prayer of USD 52,962.34 claimed as specific damages for loss of business resulted from termination of lease agreement between the plaintiff and Swissport, I would say that the loss if any, suffered by the plaintiff has not been established and even though it was established and this loss is .. not attributable or recoverable from the 2 nd defendant, I agree with the ·2 nd defendant that if there was any loss suffered by the plaintiff resulting from the lease agreement between itself and Swisspor_t, _those losses are attributable to the plaintiff . themselves due to then failure to diligently contract and take Contingency Contractual measures that usually carter for leases of buildings under construction. There was an . -admission that the plaintiff had entered into a contract with Swiss
port when the building was still under construction without,making . any precautions or·" making. . any provisions for ' ... 13 circumstai.7.ces that would · warrant extension of time to complete the work. In this case, the plaintiff is the Landlord to Swissport, and as between the landlord . and Swissport, the landlord 1s responsible for the installation of the elevator, th~ tenant will have three primary concerns: (a) getting the most work it can out of the landlord, (b) getting the landlord to stand behind its work with some sort of warranty obligation, and (c) achieving completion by a specified date. In this case, it has not been shown when was the commencement date of the lease i.e. the . . . date on which the tenant started occupying the rented floors or whether there was a clause allowing for extension of the lease period without penalty to the landlord for a.s long as it takes the landlord to complete the elevators. The landlord did not show to the court that it took some steps to c·omplete installation of the elevator in time or within the shortest possible peri~d after finding out that the 1 st defendant could not show up to do the work. Additionally, it makes someone wonder as to why Swissport agreed taking possession of the 14 two. V:oors while. tp..e building, w,as still under construction; if that happened Swiss port would have been deemed· in acceptance of the.
premises as it were i.e as is basis and that the tenant had waived any claims against the landlord for defects or delays. In any case, apart from the lease agreement presented to court, the plaintiff failed to present any claim or proof on the fact that the lease agreement was terminated and there was any claims by the tenant or any proof that another tenant was willing to occupy the top floor while the elevator was not yet installed. As submitted by the Counsel for the plaintiff, loss of business if any was not proved on the required balance of proving civil cases, and that even if the loss was proved, that loss is not at all attributed to the 2 nd defendant but to the plaintiff itself. It fallows the refore that the rest of the prayers as against the 2 nd defendant fails, and as against the 2°d defendant the suit is dismissed with costs. DATED at DAR ES SALAAM t~is 20 th day of November, 201?
15.
MANSOOR
JUDGE 20 th November 2015 16 .,.._.___.._,... __ .