[2011] EACJ 9

[2011] EACJ 9

The Court held that it has jurisdiction under Article 30(1) of the Treaty to determine the legality of the Respondent's action to construct a road across the Serengeti National Park, as the matter is not reserved to Tanzanian institutions under Article 30(3). The Court found that the Reference was filed within the...

Source-derived case information.

Citation
[2011] EACJ 9
Parties
Applicant: Africa Network for Animal Welfare (ANAW); Respondent: Attorney General of the United Republic of Tanzania
Court
East African Court of Justice
Jurisdiction
Uganda
Case Number
Reference 9 of 2010
Procedural Posture
Reference / Ruling on Preliminary Objections
Outcome
Preliminary objections overruled with costs to the Applicant.
Judges
Arach-Amoko DPJ, Busingye PJ, Butasi J, Lenaola J, Mkwawa J
Legal Topics
Treaty Interpretation, Jurisdiction of Regional Courts, Environmental Protection, Limitation of Actions
Source Language
en
Administrative Law Environmental Law Treaty Interpretation Jurisdiction of Regional Courts Environmental Protection Limitation of Actions

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 2 Party arguments 2
Sign in to unlock

Parties

Africa Network for Animal Welfare (ANAW)

Applicant

Attorney General of the United Republic of Tanzania

Respondent

Procedural Posture

Reference / Ruling on Preliminary Objections

  1. 1 Whether the East African Court of Justice has jurisdiction to determine the legality of the Respondent's action to construct a road across the Serengeti National Park under the Treaty for the Establishment of the East African Community.
  2. 2 Whether the Reference is time-barred under Article 30(2) of the Treaty.
  3. 3 Whether the Reference is properly before the Court in terms of form and procedure.

Ratio Decidendi

The Court held that it has jurisdiction under Article 30(1) of the Treaty to determine the legality of the Respondent's action to construct a road across the Serengeti National Park, as the matter is not reserved to Tanzanian institutions under Article 30(3). The Court found that the Reference was filed within the two-month limitation period, as the relevant Board minutes were dated 20th November 2010 and the Reference was filed on 10th December 2010. The use of 'Notice of Motion' in the Reference was a misapplication of the Rules but did not occasion injustice or confusion, and the Reference otherwise complied with Rule 24. The Court further held that Article 39 does not bar it from...

Court Disposition

Preliminary objections overruled with costs to the Applicant.

Orders

  • The preliminary objection is overruled in its entirety.
  • Costs awarded to the Applicant.