[2012] UGCommC 58

[2012] UGCommC 58

The court found that a valid contract (MOU) existed between the parties, and the counter defendant breached its fundamental term by failing to deposit the agreed funds. However, the counterclaimant, by accepting an alternative arrangement and not insisting on strict performance, waived its right to treat the breach...

Source-derived case information.

Citation
[2012] UGCommC 58
Parties
Plaintiff: Andes (EAS) Limited; Defendant: Akoong Wat Mulik Systems Ltd
Court
Commercial Court of Uganda
Jurisdiction
Uganda
Case Number
High Court Civil Suit No. 184 of 2008
Procedural Posture
Civil Suit / Judgment on Counterclaim After Ex Parte Hearing
Outcome
Counterclaim dismissed. No order as to costs.
Judges
Obura, J
Legal Topics
Breach of Contract, Memorandum of Understanding, Waiver and Estoppel, Damages Assessment, Mitigation of Loss
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Memorandum of Understanding Waiver and Estoppel Damages Assessment Mitigation of Loss

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 6 Authorities cited 15 Party arguments 2 Amounts and remedies 6
Sign in to unlock

Parties

Andes (EAS) Limited

Plaintiff

Akoong Wat Mulik Systems Ltd

Defendant

Procedural Posture

Civil Suit / Judgment on Counterclaim After Ex Parte Hearing

  1. 1 Whether there was a valid contract between the counterclaimant and counter defendant.
  2. 2 Whether the counter defendant breached the contract.
  3. 3 Whether the counterclaimant is entitled to the remedies sought.

Ratio Decidendi

The court found that a valid contract (MOU) existed between the parties, and the counter defendant breached its fundamental term by failing to deposit the agreed funds. However, the counterclaimant, by accepting an alternative arrangement and not insisting on strict performance, waived its right to treat the breach as repudiatory and to claim damages. The court held that waiver was established by the counterclaimant's conduct, which was inconsistent with an intention to enforce the original contract terms. Furthermore, the counterclaimant failed to mitigate its losses and did not strictly prove special damages, particularly projected profits and contingent liabilities. The claim for...

Court Disposition

Counterclaim dismissed. No order as to costs.

Orders

  • The counterclaim is dismissed.
  • No order as to costs is made.