[2023] UGEDT 2

[2023] UGEDT 2

The tribunal found that the applicant failed to establish a prima facie case warranting a temporary injunction, as the evidence did not demonstrate serious questions to be tried regarding the respondent's statutory powers or the legality of the performance bond requirement. The applicant did not provide sufficient...

Source-derived case information.

Citation
[2023] UGEDT 2
Parties
Applicant: ARPE Limited; Respondent: Electricity Regulatory Authority
Court
Electricity Disputes Tribunal
Jurisdiction
Uganda
Case Number
MISCELLENOUS APPLICANT EDT 9 of 2023
Procedural Posture
Miscellaneous Application / Ruling on Temporary Injunction
Outcome
application dismissed
Judges
Cheptoris Silvia - Registrar Electricty Disputes Tribunal
Legal Topics
Electricity Licensing, Regulatory Compliance, Environmental Performance Bond, Temporary Injunction, Licence Modification
Source Language
en
Administrative Law Commercial and Corporate Electricity Licensing Regulatory Compliance Environmental Performance Bond Temporary Injunction Licence Modification

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 8 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

ARPE Limited

Applicant

Electricity Regulatory Authority

Respondent

Procedural Posture

Miscellaneous Application / Ruling on Temporary Injunction

  1. 1 Whether the applicant is entitled to a temporary injunction to preserve the status quo of its generation licence pending determination of the complaint.
  2. 2 Whether the respondent lawfully required the applicant to post an environmental performance bond of USD 20,000 per MW.
  3. 3 Whether the applicant will suffer irreparable damage if the injunction is not granted.

Ratio Decidendi

The tribunal found that the applicant failed to establish a prima facie case warranting a temporary injunction, as the evidence did not demonstrate serious questions to be tried regarding the respondent's statutory powers or the legality of the performance bond requirement. The applicant did not provide sufficient proof of irreparable damage that could not be compensated by damages, nor did it adequately establish the status quo to be preserved. The tribunal held that the respondent, as the regulatory authority, is mandated to ensure compliance with licence conditions and environmental obligations, and its actions were within statutory powers. The balance of convenience was found to...

Court Disposition

application dismissed

Orders

  • The application for a temporary injunction is not allowed.
  • Each party shall bear its own costs.