[2024] UGHC 1145

[2024] UGHC 1145

The court found that the MOU between the parties and the defendant clearly stipulated that upon final determination of Civil Appeal No.52 of 2016, the compensation amount of Ugx 74,620,000/= would be paid to the successful party declared by court to be the owner of the land. The High Court judgment decreed the...

Source-derived case information.

Citation
[2024] UGHC 1145
Parties
Plaintiff: Bahimbiriza Bidindwale; Defendant: Total Energies E. P Uganda B. V
Court
High Court of Uganda
Jurisdiction
Uganda
Case Number
Civil Suit 36 of 2022
Procedural Posture
Civil Suit / Judgment
Outcome
judgment for the plaintiff
Judges
Byaruhanga Rugyema, J
Legal Topics
Compulsory Acquisition, Compensation for Land, Memorandum of Understanding, Interest Awards, General Damages, Ownership Disputes
Source Language
en
Land and Property Commercial and Corporate Compulsory Acquisition Compensation for Land Memorandum of Understanding Interest Awards General Damages Ownership Disputes

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 10 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

Bahimbiriza Bidindwale

Plaintiff

Total Energies E. P Uganda B. V

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether the plaintiff is entitled to Ugx 74,620,000/= from the defendant as compensation for land acquired for the Tilenga Oil Project.
  2. 2 What remedies are available to the parties.

Ratio Decidendi

The court found that the MOU between the parties and the defendant clearly stipulated that upon final determination of Civil Appeal No.52 of 2016, the compensation amount of Ugx 74,620,000/= would be paid to the successful party declared by court to be the owner of the land. The High Court judgment decreed the disputed land to the plaintiff, and no appeal was preferred by Ochaya Mugayo. The defendant's attempt to apportion the compensation based on acreage was rejected, as the MOU and the mapped land in dispute were clear and binding. The defendant's failure to file interpleader proceedings or join Ochaya Mugayo's estate further supported the plaintiff's entitlement to the full...

Court Disposition

judgment for the plaintiff

Orders

  • The defendant to pay the plaintiff the compensatory sum of Ugx 74,620,000/=.
  • The defendant to pay general damages of Ugx 25,000,000/=.