[2021] UGCommC 105
The court found that the applicant's request for access to the respondent's sites for the purpose of conducting an independent valuation of the metal works was justified by the ongoing dispute over the quantum of the contract sum. The respondent's repeated denial of access, despite multiple requests, necessitated...
Source-derived case information.
- Citation
- [2021] UGCommC 105
- Parties
- Applicant: Simon Peter Bbosa; Respondent: Geoffrey Kazinda
- Court
- Commercial Court of Uganda
- Jurisdiction
- Uganda
- Case Number
- H.C.Miscellaneous Application No. 212 of 2020
- Procedural Posture
- Miscellaneous Application / Ruling
- Outcome
- application_granted
- Judges
- Gaswaga, J
- Legal Topics
- Valuation of Contractual Works, Access to Property for Expert Assessment, Disputed Contract Sums
- Source Language
- en
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Simon Peter Bbosa
Applicant
Geoffrey Kazinda
Respondent
Procedural Posture
Miscellaneous Application / Ruling
Legal Issues
- 1 Whether leave should be granted to the applicant to access the respondent's sites at Kitala I & II and at Kisubi to enable a Valuation Surveyor to carry out a valuation of the metal works installed by the applicant.
Ratio Decidendi
The court found that the applicant's request for access to the respondent's sites for the purpose of conducting an independent valuation of the metal works was justified by the ongoing dispute over the quantum of the contract sum. The respondent's repeated denial of access, despite multiple requests, necessitated judicial intervention. The court held that allowing an independent expert to assess the works was essential for a fair determination of the case, and that such access would not prejudice the respondent since the main suit had not yet commenced. The application was unopposed and the court exercised its inherent powers under Section 98 of the Civil Procedure Act to grant the orders...
Court Disposition
application_granted
Orders
- The respondent shall grant the applicant access to the sites at Kitala I & II and Kisubi, Wakiso District to enable a Valuation Surveyor to carry out a valuation of the metal works installed by the applicant.
- Costs of this application shall be in the main cause.
Full Case Text
Judgment text and source record
22 paragraphs
# **THE REPUBLIC OF UGANDA**
# **IN THE HIGH COURT OF UGANDA AT KAMPALA**
# **[COMMERCIAL COURT]**
### **M. A No. 212 OF 2020**
### **(Arising out of HCCS No. 150 of 2012)**
# **SIMON PETER BBOSA:::::::::::::::::::::::::::::::::APPLICANT/PLAINTIFF**
## **VERSUS**
**GEOFFREY KAZINDA::::::::::::::::::::::::::::RESPONDENT/DEFENDANT**
### **BEFORE: HON. JUSTICE DUNCAN GASWAGA**
#### **RULING**
- [1] This is a ruling on an application brought under Section 98 CPA and Order 52 rules 1&2 CPR for orders that; *the applicant be granted leave to access the respondent's sites at Kitala (I) & (II) and at Kisubi, Wakiso District to enable a Valuation Surveyor to carry out a valuation of the metal works that the applicant carried out/ installed at the said sites; the respondent or his agents or representatives be directed to grant the applicant or his agents access to the respondent's sites/premises at Kitala (l)&(ll) and at Kisubi, Wakiso District to enable a Valuation Surveyor to carry out a valuation of the metal works installed by the applicant on those sites/premises and for costs of this application.* - [2] The grounds of the application were detailed in the affidavit of Simon Peter Bbosa and they were briefly that; the applicant filed HCCS No.
- 150 of 2012 against the respondent/defendant for payment of an outstanding balance on the contract price of metal works installed by the applicant on the respondent's site at Kitala <sup>I</sup> & II and at Kisubi, Wakiso District. That in the respondent's defence he stated that the value of the works executed by the applicant was assessed by SM Cathan at Ugx 319, 276,850/= and that the cost of completing the said works was Ugx 24,587,000/= as opposed to the Ugx 403,098,000/= that was being demanded by the applicant. This dispute in amount justifies the applicant's need to instruct his own valuation surveyor to carry out a valuation so as to assess the quantum/ value of metal works installed by the applicant on the said premises. Further, that the said valuation will aid court in reaching a fair and just conclusion in this case upon comparison with the respondent's valuation report. The respondent has on numerous occasions denied the applicant's valuation surveyor access to the said premises despite various requests but granting of these orders by this court would not prejudice the respondent since the hearing of the said case has not kicked off and it is just and fair that the application be granted. - [3] At the hearing of the application, the respondent did not appear in court and so did his lawyer despite service of court process on them. Court then granted the applicant leave to proceed exparte by way of written submissions. - [4] This application raises one issue;
*Whether leave should be granted to the applicant to access the respondent's sites at Kitala I & II and at Kisubi, the subject of HCCS No. 150 of 2012, to enable a Valuation Surveyorto carry out*
# *a valuation ofthe metal works comprised thereon on behalfofthe applicant.*
- [5] It was submitted by Counsel for the applicant that it is necessary to have valuation of the existing metal works done by the applicant by an independent expert in order to secure a distinct expert opinion on the matter following the dispute on the value of the metal works. Such independent expert valuation would then assist court in evaluating the technical evidence on the quantum presented by both parties to the dispute. The applicant's submission was supported by Section 98 CPA and the case of **Ayub Suleiman Vs Salim Kabambalo, SCCA 32 of 1995** wherein it was stated interalia that; "in respect of the inherent powers of court under the then Section 101 of the Civil Procedure Act, *that court can always invoke its inherent power to make orders that are necessary for the ends ofjustice or to prevent abuse of the process of court."The* applicant further prayed for costs under Section 27(2) CPA for the respondent's frustration of the valuation process through continuously ignoring the requests for the same. - [6] <sup>I</sup> have carefully perused the pleadings and submissions on the record of court. It is apparent that the applicant sued the respondent for recovery of monies for payment of metal works executed by the applicant on the respondent's premises however, the monies involved are disputed hence the need for a valuation. Despite the various requests by the applicant to the respondent, the same has not been possible, the reason for the said application. Indeed the assessment and valuation of the works so far done on the premises would go a long way in assisting the court to reach a just decision. This cannot be done without allowing another or independent expert to access the premises
in question and carry out the valuation. <sup>I</sup> therefore find merit in the applicant's submission which stands unopposed.
**[7] Accordingly, this application is granted. Pursuant to Section 98 of the Civil Procedure Act, <sup>I</sup> hereby order that the respondent grants access to the applicant to have the valuation of the metal works carried out. In the interest of justice it is ordered that the costs of this application shall be in the main cause.**
**<sup>I</sup> so order**
i
**Dated, signed and delivered at Kampala this 46tfi day of August, 2021**
**Dunc^n^daswaga**
**JUDGE**