[2025] UGCommC 18

[2025] UGCommC 18

The court found that the contract executed between the parties was a lump sum contract, as evidenced by the signed agreement and the Plaintiff's knowledge of the change from admeasurement to lump sum prior to signing. The Plaintiff was bound by the terms of the written agreement, and no credible evidence was adduced...

Source-derived case information.

Citation
[2025] UGCommC 18
Parties
Plaintiff: Benar Technical Services Limited; Defendant: National Curriculum Development Centre
Court
Commercial Court of Uganda
Jurisdiction
Uganda
Case Number
Civil Suit 396 of 2013
Procedural Posture
Civil Suit / Judgment
Outcome
Both the suit and the counterclaim are dismissed. Each party shall bear its own costs.
Judges
Tumusiime Rubagumya, J
Legal Topics
Breach of Contract, Public Procurement, Contract Interpretation, Special Damages, Remedies, Evidence Standard
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Public Procurement Contract Interpretation Special Damages Remedies Evidence Standard

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 12 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Benar Technical Services Limited

Plaintiff

National Curriculum Development Centre

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether the contract entered into by the Plaintiff and the Defendant was a lump sum or admeasurement contract.
  2. 2 Whether the Bill of Quantities presented by the Defendant to the Plaintiff was under measured.
  3. 3 Whether the Plaintiff is entitled to the payment for the extra work done in execution and completion of the contract.

Ratio Decidendi

The court found that the contract executed between the parties was a lump sum contract, as evidenced by the signed agreement and the Plaintiff's knowledge of the change from admeasurement to lump sum prior to signing. The Plaintiff was bound by the terms of the written agreement, and no credible evidence was adduced to prove that the Bill of Quantities was under measured or that extra work was authorized and executed beyond the contract scope. The Plaintiff's claim for extra payment failed as the contract price was fixed and the Defendant did not authorize any variation. Similarly, the Defendant's counterclaim for special damages failed due to lack of strict proof and supporting evidence....

Court Disposition

Both the suit and the counterclaim are dismissed. Each party shall bear its own costs.

Orders

  • The suit is hereby dismissed.
  • The counterclaim is hereby dismissed.