[1993] UGHC 91

[1993] UGHC 91

The court found that the contract for the supply of agricultural implements was between the plaintiff and Messey Furguson (U.K.), not the defendant, who acted only as a facilitator. The essential elements of contract—offer, acceptance, and consideration—were present between the plaintiff and the supplier, not the...

Source-derived case information.

Citation
[1993] UGHC 91
Parties
Plaintiff: Birumi Wilson; Defendant: Akamba (U) Ltd.
Court
High Court of Uganda
Jurisdiction
Uganda
Case Number
Civil Suit No. 152 of 1991
Procedural Posture
Civil Suit / Judgment
Outcome
suit dismissed
Judges
GM OKELLO, J
Legal Topics
Agency Liability, Breach of Contract, Special Damages, Contract Formation
Source Language
en
Commercial and Corporate Agency Liability Breach of Contract Special Damages Contract Formation

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 1 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Birumi Wilson

Plaintiff

Akamba (U) Ltd.

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether there was a contract between the plaintiff and the defendant.
  2. 2 Whether the defendant undertook to deliver the agricultural implements within three months.
  3. 3 Whether the defendant is liable for the delay in delivery of the Tiller.

Ratio Decidendi

The court found that the contract for the supply of agricultural implements was between the plaintiff and Messey Furguson (U.K.), not the defendant, who acted only as a facilitator. The essential elements of contract—offer, acceptance, and consideration—were present between the plaintiff and the supplier, not the defendant. The defendant did not undertake to deliver the Tiller within a specific timeframe, and any guidance given was not a contractual commitment. The plaintiff failed to strictly prove special damages, as his evidence lacked specificity and cogency. Consequently, the defendant was not liable for the delay, and the plaintiff was not entitled to remedies against the defendant.

Court Disposition

suit dismissed

Orders

  • The suit is dismissed with costs to the defendant.