[2024] UGCommC 334

[2024] UGCommC 334

The Plaintiff failed to complete the contractual works within the stipulated time as amended by the Addendum, which made time of the essence. The Addendum superseded earlier timelines, and the Plaintiff, by signing, acknowledged the new completion period. The Plaintiff's subsequent hardships were not sufficiently...

Source-derived case information.

Citation
[2024] UGCommC 334
Parties
Plaintiff: Damuco Investments Ltd.; Defendant: Opportunity Bank (U) Ltd.
Court
Commercial Court of Uganda
Jurisdiction
Uganda
Case Number
Civil Suit 589 of 2019
Procedural Posture
Civil Suit / Judgment
Outcome
Judgment for the Defendant/Counter-Claimant on the counterclaim; Plaintiff's suit dismissed.
Judges
Harriet Grace Magala, J
Legal Topics
Breach of Contract, Construction Contracts, Penalty Clauses, Special and General Damages
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Construction Contracts Penalty Clauses Special and General Damages

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 17 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Damuco Investments Ltd.

Plaintiff

Opportunity Bank (U) Ltd.

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether the Defendant breached the two construction contracts dated 7th March 2018 for construction of ATM rooms and painting of the Defendant's branches.
  2. 2 Whether the Plaintiff/Counter-defendant is liable on the counterclaim.
  3. 3 What remedies are available to the parties.

Ratio Decidendi

The Plaintiff failed to complete the contractual works within the stipulated time as amended by the Addendum, which made time of the essence. The Addendum superseded earlier timelines, and the Plaintiff, by signing, acknowledged the new completion period. The Plaintiff's subsequent hardships were not sufficiently communicated or proven to have been caused by the Defendant. The Defendant's termination of the ATM rooms contract was justified by the Plaintiff's failure to perform within the agreed period. The contract for painting was not terminated and could be performed independently. The Plaintiff's claim for breach and special damages was unsupported, as the Plaintiff had already...

Court Disposition

Judgment for the Defendant/Counter-Claimant on the counterclaim; Plaintiff's suit dismissed.

Orders

  • Declaration that the Defendant/Counter-Claimant did not breach the contracts dated 7th March 2018.
  • Declaration that the Plaintiff/Counter-Defendant is liable for breach of contract.