[2024] UGHC 901

[2024] UGHC 901

The court found that although the arbitral award was delivered approximately 15 days beyond the statutory two-month period, the applicants participated in the proceedings, failed to object to the delay, and thus waived their right to challenge the award on that ground under section 4 of the Arbitration and...

Source-derived case information.

Citation
[2024] UGHC 901
Parties
Applicant: Elgonia One Café International Ltd; Applicant: Bukawa Cassim Musene; Applicant: Wakikona John; Applicant: Elgonia Industries Ltd; Respondent: Stanbic Bank Uganda Limited; Respondent: ACE-Audit Control & Expertise Limited (ACE-Global)
Court
High Court of Uganda
Jurisdiction
Uganda
Case Number
Miscellaneous Application 259 of 2020
Procedural Posture
Miscellaneous Application / Ruling
Outcome
application dismissed
Judges
Apiny, J
Legal Topics
Arbitral Award Setting Aside, Arbitration Agreement Scope, Joinder of Parties, Waiver of Objection, Privity of Contract, Group of Companies Doctrine
Source Language
en
Civil Procedure Commercial and Corporate Alternative Dispute Resolution Arbitral Award Setting Aside Arbitration Agreement Scope Joinder of Parties Waiver of Objection Privity of Contract +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 7 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Elgonia One Café International Ltd

Applicant

Bukawa Cassim Musene

Applicant

Wakikona John

Applicant

Elgonia Industries Ltd

Applicant

Stanbic Bank Uganda Limited

Respondent

ACE-Audit Control & Expertise Limited (ACE-Global)

Respondent

Procedural Posture

Miscellaneous Application / Ruling

  1. 1 Whether the arbitral award was delivered out of time contrary to the Arbitration and Conciliation Act.
  2. 2 Whether the award contains matters beyond the scope of reference of the arbitration.
  3. 3 Whether the orders made against the 4th applicant are valid given it was not a party to the arbitration agreement or reference.

Ratio Decidendi

The court found that although the arbitral award was delivered approximately 15 days beyond the statutory two-month period, the applicants participated in the proceedings, failed to object to the delay, and thus waived their right to challenge the award on that ground under section 4 of the Arbitration and Conciliation Act. The court further held that the arbitrator did not exceed the scope of reference, as the Field Warehouse and Storage Agreement and the Agricultural Loan Facility Agreement were inextricably linked, and the disputes arising from both were properly arbitrated. The 2nd, 3rd, and 4th applicants, though not original signatories, were joined by consent and are bound under...

Court Disposition

application dismissed

Orders

  • The application to set aside the arbitral award is dismissed with costs.
  • The arbitral award dated 26th October 2020 remains valid and enforceable.