[2020] UGCommC 8

[2020] UGCommC 8

The court found that the Arbitrator did not have jurisdiction to entertain the dispute because the contract required disputes arising from the Project Manager's decisions to be referred first to an Adjudicator under Clause 24.1 GCC. Only after the Adjudicator's decision could the matter be appealed to arbitration...

Source-derived case information.

Citation
[2020] UGCommC 8
Parties
Applicant: Fort Portal Municipal Council; Respondent: Plinth Technical Works Ltd
Court
Commercial Court of Uganda
Jurisdiction
Uganda
Case Number
Miscellaneous Application No. 231 of 2019
Procedural Posture
Miscellaneous Application / Ruling
Outcome
application_granted
Judges
Adonyo, J
Legal Topics
Arbitration Jurisdiction, Contractual Dispute Resolution, Adjudication Procedure, Interpretation of Contract Clauses
Source Language
en
Civil Procedure Commercial and Corporate Arbitration Jurisdiction Contractual Dispute Resolution Adjudication Procedure Interpretation of Contract Clauses

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 6 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Fort Portal Municipal Council

Applicant

Plinth Technical Works Ltd

Respondent

Procedural Posture

Miscellaneous Application / Ruling

  1. 1 Whether the Arbitrator had jurisdiction to entertain the arbitration claims when the dispute was already under adjudication or at all.
  2. 2 Whether the Arbitrator exceeded his jurisdiction by exercising powers and making pronouncements reserved for the Adjudicator.
  3. 3 Whether the Arbitrator improperly determined that he is entitled to entertain compensation claims and claims arising from paid certificates which have not been subject to adjudication under Clause 24.1 GCC.

Ratio Decidendi

The court found that the Arbitrator did not have jurisdiction to entertain the dispute because the contract required disputes arising from the Project Manager's decisions to be referred first to an Adjudicator under Clause 24.1 GCC. Only after the Adjudicator's decision could the matter be appealed to arbitration under Clause 25.3 GCC. The Arbitrator's interpretation that he had original jurisdiction under Clause 25.4 was incorrect, as this clause is procedural and does not override the requirement for adjudication. The Arbitrator's decision to proceed with the arbitration was premature and contrary to the contract's dispute resolution mechanism. Therefore, the Arbitrator's decision on...

Court Disposition

application_granted

Orders

  • The Arbitrator is not vested with jurisdiction to hear and determine the claim under Clause 24 and Clause 25.4 of the GCC until after determination by the Adjudicator under Clause 24 in original jurisdiction.
  • The decision of the Arbitrator dated 12th March 2019 on jurisdiction is set aside.