[2018] UGSC 19

[2018] UGSC 19

The Supreme Court held that under the Public Procurement and Disposal of Public Assets Act, a contract between a procuring entity and a provider is only formed upon strict compliance with statutory procedures, including the execution of a formal written contract after all conditions are satisfied. The letter of bid...

Source-derived case information.

Citation
[2018] UGSC 19
Parties
Appellant: Galleria in Africa Limited; Respondent: Uganda Electricity Distribution Company Limited
Court
Supreme Court of Uganda
Jurisdiction
Uganda
Case Number
Civil Appeal 8 of 2017
Procedural Posture
Civil Appeal / Supreme Court Final Judgment
Outcome
appeal dismissed, cross-appeal allowed
Judges
Mwondha, JSC, Arach-Amoko, JSC, Mwangusya, JSC, Opio-Aweri, JSC, Tibatemwa-Ekirikubinza, JSC
Legal Topics
Public Procurement, Contract Formation, Breach of Contract, Damages Quantum, Statutory Compliance
Source Language
en
Commercial and Corporate Civil Procedure Public Procurement Contract Formation Breach of Contract Damages Quantum Statutory Compliance

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 8 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

Galleria in Africa Limited

Appellant

Uganda Electricity Distribution Company Limited

Respondent

Procedural Posture

Civil Appeal / Supreme Court Final Judgment

  1. 1 Whether there was a valid and binding contract concluded between the parties under the PPDA Act and Regulations.
  2. 2 Whether the letter of bid acceptance constituted a contract under Ugandan procurement law.
  3. 3 Whether the appellant was entitled to damages for lost profit and whether the general damages awarded were adequate.

Ratio Decidendi

The Supreme Court held that under the Public Procurement and Disposal of Public Assets Act, a contract between a procuring entity and a provider is only formed upon strict compliance with statutory procedures, including the execution of a formal written contract after all conditions are satisfied. The letter of bid acceptance, even if unequivocal, does not itself create a binding contract unless followed by the signing of a formal contract document as required by section 76(3) of the PPDA Act. The Court found that the conditions precedent to contract formation were not met, as there was no evidence that the contracts committee had delegated adjudication powers to the accounting officer or...

Court Disposition

appeal dismissed, cross-appeal allowed

Orders

  • The appeal is dismissed.
  • The cross-appeal is allowed.