[2024] UGCommC 388

[2024] UGCommC 388

The Defendants obtained two secured loan facilities from the Plaintiff, executed personal guarantees, and defaulted on repayment obligations. The Plaintiff adduced documentary evidence of the loan agreements, guarantees, and notices of default. The Defendants failed to file a defence or respond to the Plaintiff's...

Source-derived case information.

Citation
[2024] UGCommC 388
Parties
Plaintiff: I & M Bank Uganda Limited; Defendant: Pluto Pharmaceuticals Limited; Defendant: Mirza Irshad Ali Baig; Defendant: Muhammed Aslam Arfath
Court
Commercial Court of Uganda
Jurisdiction
Uganda
Case Number
Civil Suit No. 471 of 2024
Procedural Posture
Civil Suit / Judgment
Outcome
judgment for the plaintiff
Judges
Tumusiime Rubagumya, J
Legal Topics
Loan Facility Breach, Guarantee Liability, Interest Award, General Damages, Contract Enforcement
Source Language
en
Banking and Finance Commercial and Corporate Loan Facility Breach Guarantee Liability Interest Award General Damages Contract Enforcement

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 16 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

I & M Bank Uganda Limited

Plaintiff

Pluto Pharmaceuticals Limited

Defendant

Mirza Irshad Ali Baig

Defendant

Muhammed Aslam Arfath

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether the Defendants breached the terms of the facility agreement entered with the Plaintiff.
  2. 2 What remedies are available to the parties.

Ratio Decidendi

The Defendants obtained two secured loan facilities from the Plaintiff, executed personal guarantees, and defaulted on repayment obligations. The Plaintiff adduced documentary evidence of the loan agreements, guarantees, and notices of default. The Defendants failed to file a defence or respond to the Plaintiff's claims. The court found that the Defendants breached the terms of the facility agreement and the guarantees, making them jointly and severally liable for the outstanding sum. The Plaintiff is entitled to recover the principal sum, general damages, interest at the contractual rate on the principal, and interest at a reasonable rate on general damages. Costs of the suit are also...

Court Disposition

judgment for the plaintiff

Orders

  • The Defendants are jointly and severally liable for breach of the loan facility agreement.
  • The Defendants shall pay to the Plaintiff UGX 128,158,278, being the outstanding sum due on account of breach.