[2018] UGEDT 4

[2018] UGEDT 4

The Respondent unlawfully connected 12 other customers to the Complainant's meter, breaching its statutory duty under Regulation 7.1.1(b) of the Electricity (Primary Grid Code) Regulation 2003 to provide and maintain standard metering equipment. This act constituted actionable negligence, resulting in overbilling...

Source-derived case information.

Citation
[2018] UGEDT 4
Parties
Complainant: Kamba Petroleum (U) Limited; Respondent: Umeme (U) Limited
Court
Electricity Disputes Tribunal
Jurisdiction
Uganda
Case Number
EDT COMPLAINT 10 of 2016
Procedural Posture
Complaint / Final Judgment
Outcome
complaint partially upheld
Judges
Charles Okoth Owor - Chairperson Electricity Disputes Tribunal, Anaclet Turyakira, - Vice Chair Person Electricty Disputes Tribunal, Eng. Dr. Moses Musaazi - Member Electricity Disputes Tribunal
Legal Topics
Electricity Distribution Liability, Metering Equipment Standards, Negligence in Service Provision, General Damages Assessment
Source Language
en
Commercial and Corporate Tort Law Electricity Distribution Liability Metering Equipment Standards Negligence in Service Provision General Damages Assessment

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 6 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Kamba Petroleum (U) Limited

Complainant

Umeme (U) Limited

Respondent

Procedural Posture

Complaint / Final Judgment

  1. 1 Whether the Respondent unlawfully connected other customers to the Complainant's meter.
  2. 2 Whether the Respondent overcharged the Complainant's meter.
  3. 3 Whether the Complainant is entitled to the remedies sought.

Ratio Decidendi

The Respondent unlawfully connected 12 other customers to the Complainant's meter, breaching its statutory duty under Regulation 7.1.1(b) of the Electricity (Primary Grid Code) Regulation 2003 to provide and maintain standard metering equipment. This act constituted actionable negligence, resulting in overbilling and loss to the Complainant. Although the precise quantum of special damages was not pleaded or proved, the tribunal found sufficient evidence of loss and inconvenience to award general damages. The Respondent's remedial actions did not negate its initial breach or the resulting harm. The tribunal declined to award special damages due to lack of specific pleading and proof but...

Court Disposition

complaint partially upheld

Orders

  • The connection of other customers to the Complainant's meter was unlawful.
  • The Complainant's meter was overcharged.