[1994] UGHC 28

[1994] UGHC 28

The court found that the plaintiff completed the contracted work and was entitled to payment, but the amount claimed did not tally with the work done after proper deductions for advance payments, retention, and the cost of materials supplied by the defendant. The court accepted oral evidence of an extension of time...

Source-derived case information.

Citation
[1994] UGHC 28
Parties
Plaintiff: Kanoblic Group of Companies (U); Defendant: Sugar Corporation of Uganda Ltd.
Court
High Court of Uganda
Jurisdiction
Uganda
Case Number
H.C.C.S. 299 of 1993
Procedural Posture
Civil Suit / Judgment
Outcome
Plaintiff's claim allowed in part; defendant to pay balance due; no order as to costs.
Judges
Okello, J
Legal Topics
Breach of Contract, Construction Contracts, Assessment of Damages, Fraud Allegations, Contract Variation, Penalty Clauses
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Construction Contracts Assessment of Damages Fraud Allegations Contract Variation Penalty Clauses

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 3 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Kanoblic Group of Companies (U)

Plaintiff

Sugar Corporation of Uganda Ltd.

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether the amount of money claimed by the plaintiff tallies with the work done by them.
  2. 2 Whether or not there was work uncompleted by the plaintiff worth Uganda Shs.405,100/=.
  3. 3 Whether the defendant was fraudulent.

Ratio Decidendi

The court found that the plaintiff completed the contracted work and was entitled to payment, but the amount claimed did not tally with the work done after proper deductions for advance payments, retention, and the cost of materials supplied by the defendant. The court accepted oral evidence of an extension of time for completion due to increased scope of work, as this was not inconsistent with the written contract. The defendant was not under a contractual obligation to supply materials, and any delay in supply did not constitute a breach. Allegations of fraud by the defendant in inflating material quantities and prices, and charging a 10% handling fee, were not proved to the required...

Court Disposition

Plaintiff's claim allowed in part; defendant to pay balance due; no order as to costs.

Orders

  • Defendant to pay the plaintiff Uganda Shs. 313,408/=.
  • Each party to bear its own costs of the suit.