[2015] UGEDT 2

[2015] UGEDT 2

The Tribunal found that the Respondent was in breach of its statutory duty to supply electricity by failing to restore power to the Complainant for two years, despite being under a legal obligation to do so. The Respondent's evidence was inconsistent with its pleadings and the agreed facts, particularly regarding...

Source-derived case information.

Citation
[2015] UGEDT 2
Parties
Complainant: Kasajja Thomas; Respondent: Umeme Limited
Court
Electricity Disputes Tribunal
Jurisdiction
Uganda
Case Number
EDT COMPLAINT 2 of 2009
Procedural Posture
Complaint / Judgment
Outcome
Complaint partially upheld; general damages and partial costs awarded to the Complainant.
Judges
Charles Okoth Owor - Chairperson Electricity Disputes Tribunal, Anaclet Turyakira, - Vice Chair Person Electricty Disputes Tribunal, Eng. Dr. Moses Musaazi - Member Electricity Disputes Tribunal
Legal Topics
Electricity Supply Disputes, Statutory Duties of Licensees, Negligence in Service Provision, General and Special Damages
Source Language
en
Land and Property Civil Procedure Electricity Supply Disputes Statutory Duties of Licensees Negligence in Service Provision General and Special Damages

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 10 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Kasajja Thomas

Complainant

Umeme Limited

Respondent

Procedural Posture

Complaint / Judgment

  1. 1 Whether the Respondent was in breach of their statutory duty and obligation.
  2. 2 Whether the disconnection of the Complainant's power supply was done by the Respondent and if so whether it was unjustified and unreasonable.
  3. 3 Whether the Respondent continued to charge the complainant for the electricity during the period of electricity supply cutoff.

Ratio Decidendi

The Tribunal found that the Respondent was in breach of its statutory duty to supply electricity by failing to restore power to the Complainant for two years, despite being under a legal obligation to do so. The Respondent's evidence was inconsistent with its pleadings and the agreed facts, particularly regarding the timing of the disconnection and restoration. The Tribunal rejected the Respondent's claim that it only became aware of the issue in 2009, noting that its own systems should have detected the fault. The continued charging of service fees during the period of disconnection was found to be lawful under the Electricity Act, as the meter and equipment remained on the premises. The...

Court Disposition

Complaint partially upheld; general damages and partial costs awarded to the Complainant.

Orders

  • The Respondent shall pay the Complainant UGX 1,500,000 as general damages for inconvenience and loss suffered.
  • The Respondent shall bear three-quarters of the costs of the proceedings.