[2018] UGEDT 8

[2018] UGEDT 8

The tribunal found that the applicant had made genuine efforts to settle part of the outstanding bill and acknowledged at least partial liability. Given that the applicant's business is his sole source of income and that he is willing to pay current bills, it was deemed fair and reasonable to order interim...

Source-derived case information.

Citation
[2018] UGEDT 8
Parties
Applicant: Katakuwange M. Fred; Respondent: Umeme Ltd
Court
Electricity Disputes Tribunal
Jurisdiction
Uganda
Case Number
MISCELLENOUS APPLICANT EDT 19 of 2017
Procedural Posture
Miscellaneous Application / Interlocutory Application
Outcome
Interim reconnection of electricity supply granted subject to deposit and payment of current bills.
Judges
Charles Okoth Owor - Chairperson Electricity Disputes Tribunal, Anaclet Turyakira, - Vice Chair Person Electricty Disputes Tribunal, Eng. Dr. Moses Musaazi - Member Electricity Disputes Tribunal
Legal Topics
Interim Injunctions, Electricity Supply Disputes, Outstanding Bills, Reconnection Orders
Source Language
en
Civil Procedure Commercial and Corporate Interim Injunctions Electricity Supply Disputes Outstanding Bills Reconnection Orders

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

Katakuwange M. Fred

Applicant

Umeme Ltd

Respondent

Procedural Posture

Miscellaneous Application / Interlocutory Application

  1. 1 Whether the applicant is entitled to an interim order for reconnection of electricity supply pending final determination of the complaint.
  2. 2 Whether the applicant should be required to make a deposit or payment towards the outstanding bill as a condition for reconnection.

Ratio Decidendi

The tribunal found that the applicant had made genuine efforts to settle part of the outstanding bill and acknowledged at least partial liability. Given that the applicant's business is his sole source of income and that he is willing to pay current bills, it was deemed fair and reasonable to order interim reconnection of electricity supply to his premises. However, this was conditioned on the applicant making a deposit of UGX 500,000 towards the outstanding bill and continuing to pay current bills as they fall due. The tribunal balanced the interests of both parties, ensuring the applicant could operate his business while safeguarding the respondent's right to recover arrears.

Court Disposition

Interim reconnection of electricity supply granted subject to deposit and payment of current bills.

Orders

  • The respondent shall reconnect electricity supply to the applicant's milling factory upon payment of a deposit of UGX 500,000 towards the outstanding bill.
  • The applicant shall pay all current bills as they fall due.