[2014] UGCommC 231

[2014] UGCommC 231

The court found that the Defendant was liable to the Plaintiff for the sum of Ug. Shs. 142,935,100/=, as established by the jointly commissioned KSK audit report, which confirmed the Defendant's indebtedness for fuel supplied. The Plaintiff's claim for additional amounts was supported by documentary evidence and...

Source-derived case information.

Citation
[2014] UGCommC 231
Parties
Plaintiff: Kironde Ashraf; Defendant: Don Uganda Ltd
Court
Commercial Court of Uganda
Jurisdiction
Uganda
Case Number
Civil Suit CS 365 of 2010
Procedural Posture
Civil Suit / Judgment
Outcome
judgment for the plaintiff; counterclaim dismissed
Judges
Adonyo, J
Legal Topics
Contractual Liability, Sale of Goods, Credit Transactions, Interest Awards
Source Language
en
Commercial and Corporate Civil Procedure Contractual Liability Sale of Goods Credit Transactions Interest Awards

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 11 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Kironde Ashraf

Plaintiff

Don Uganda Ltd

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether the Defendant is liable to the Plaintiff in the sums claimed in the plaint.
  2. 2 Whether the Plaintiff is liable to the Defendant in the sum claimed in the counterclaim.
  3. 3 Whether the Defendant was depositing money for fuel ordered on the Plaintiff's account in advance prior to supply.

Ratio Decidendi

The court found that the Defendant was liable to the Plaintiff for the sum of Ug. Shs. 142,935,100/=, as established by the jointly commissioned KSK audit report, which confirmed the Defendant's indebtedness for fuel supplied. The Plaintiff's claim for additional amounts was supported by documentary evidence and corroborated by the audit report and Uganda Revenue Authority records. The Defendant's counterclaim failed because the evidence showed that the Plaintiff had supplied the fuel for which payment was claimed, and the Defendant had received it. The court exercised its discretion to award interest at a commercial rate of 23% per annum from the date of default until payment in full,...

Court Disposition

judgment for the plaintiff; counterclaim dismissed

Orders

  • The Defendant shall pay the Plaintiff Ug. Shs. 142,935,100/=
  • Interest thereon at 23% per annum from the date of default until payment in full.