[2018] UGCommC 83

[2018] UGCommC 83

The court found that the Plaintiff supplied building materials to the Defendant under an oral contract, with deliveries evidenced by signed delivery notes and goods received notes. The Defendant's claim that some deliveries were not made or were fraudulent was unsupported by credible evidence, as the Defendant...

Source-derived case information.

Citation
[2018] UGCommC 83
Parties
Plaintiff: Kyadok Hardware Limited; Defendant: Kwik Build Contractors Ltd
Court
Commercial Court of Uganda
Jurisdiction
Uganda
Case Number
Civil Suit No. 40 of 2014
Procedural Posture
Civil Suit / Judgment
Outcome
Judgment for the Plaintiff. Counterclaim dismissed.
Legal Topics
Sale of Goods, Oral Contracts, Special Damages, General Damages, Burden of Proof
Source Language
en
Commercial and Corporate Civil Procedure Sale of Goods Oral Contracts Special Damages General Damages Burden of Proof

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 6 Authorities cited 13 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

Kyadok Hardware Limited

Plaintiff

Kwik Build Contractors Ltd

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether the Defendant is indebted to the Plaintiff in the sum claimed in the plaint.
  2. 2 Whether the Plaintiff was paid in excess of Shs. 28,497,400/- as claimed in the counter claim.
  3. 3 What remedies are available to the parties.

Ratio Decidendi

The court found that the Plaintiff supplied building materials to the Defendant under an oral contract, with deliveries evidenced by signed delivery notes and goods received notes. The Defendant's claim that some deliveries were not made or were fraudulent was unsupported by credible evidence, as the Defendant failed to call site personnel to testify and relied on unsubstantiated allegations. The Plaintiff proved, through documentary evidence, that it supplied goods worth Shs. 862,748,800/-, of which Shs. 668,497,400/- was paid, leaving a balance of Shs. 194,251,400/-. The Defendant failed to prove any overpayment. The court held that the Plaintiff was entitled to the unpaid balance as...

Court Disposition

Judgment for the Plaintiff. Counterclaim dismissed.

Orders

  • The Defendant to pay the Plaintiff special damages of Shs. 194,251,400/-.
  • The Defendant to pay the Plaintiff general damages of Shs. 10,000,000/-.