[2020] UGPPDPAAT 3

[2020] UGPPDPAAT 3

The Tribunal found that the 1st Respondent erred in declining to handle the Applicant's complaint on the basis of late payment of administrative review fees. The procurement was divided into lots, and the PPDA Guidelines required the Accounting Officer to provide guidance on the fee amount, which the Applicant paid...

Source-derived case information.

Citation
[2020] UGPPDPAAT 3
Parties
Applicant: Kyakuwaire Business Enterprises Limited; Respondent: Public Procurement and Disposal of Public Assets Authority; Respondent: Ministry of Water & Environment
Court
Public Procurement and Disposal of Public Assets Appeals Tribunal
Jurisdiction
Uganda
Case Number
Application 4 of 2020
Procedural Posture
Administrative Review Application / Final Decision
Outcome
application succeeds in part
Judges
Olive Zaare Otete - Chairperson, Moses Jurua Adriko SC - Panel Member, Abraham Nkata - Member, Isanga, Panel Member
Legal Topics
Public Procurement, Administrative Review, Contract Nullification, Statutory Compliance
Source Language
en
Administrative Law Commercial and Corporate Public Procurement Administrative Review Contract Nullification Statutory Compliance

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 5 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Kyakuwaire Business Enterprises Limited

Applicant

Public Procurement and Disposal of Public Assets Authority

Respondent

Ministry of Water & Environment

Respondent

Procedural Posture

Administrative Review Application / Final Decision

  1. 1 Whether the 1st Respondent erroneously declined to handle and grant remedies due to the Applicant on the pretext that administrative review fees were not paid in time.
  2. 2 Whether the 1st Respondent failed to comply with Section 91(4) of the PPDA Act when it failed to issue its decision within twenty-one working days after receiving the Applicant's complaint.
  3. 3 What remedies are available to the parties.

Ratio Decidendi

The Tribunal found that the 1st Respondent erred in declining to handle the Applicant's complaint on the basis of late payment of administrative review fees. The procurement was divided into lots, and the PPDA Guidelines required the Accounting Officer to provide guidance on the fee amount, which the Applicant paid promptly upon receiving such guidance. The Tribunal distinguished the cited precedent (M/S ETC Agro Tractors and Implements Ltd vs PPDA) because, unlike in that case, the Applicant here paid the fee as soon as advised. Regarding the timeline for issuing a decision, the Tribunal accepted that the COVID-19 lockdown constituted extraordinary circumstances that justified the delay,...

Court Disposition

application succeeds in part

Orders

  • The decision of the 1st Respondent is set aside.
  • The contract signed between the 2nd Respondent and Bresun Enterprises (U) Ltd is declared void ab initio and set aside.