[2023] UGCommC 243

[2023] UGCommC 243

The court found that a valid and binding contract existed between the parties, supported by the quotation and partial performance. The Defendant breached the contract by failing to complete the subdivision and titling of plots within the stipulated 59 working days. However, the Plaintiff also breached the contract...

Source-derived case information.

Citation
[2023] UGCommC 243
Parties
Plaintiff: Lakeville Investments Limited; Defendant: Mat & Spencer Limited
Court
Commercial Court of Uganda
Jurisdiction
Uganda
Case Number
Civil Suit 960 of 2018
Procedural Posture
Civil Suit / Judgment
Outcome
Suit partially succeeds; declaration of breach granted; nominal damages awarded; other claims denied; each party to bear own costs.
Judges
Anna B. Mugenyi, J
Legal Topics
Breach of Contract, Land Development Agreements, Contractual Damages, Reputational Harm
Source Language
en
Commercial and Corporate Land and Property Breach of Contract Land Development Agreements Contractual Damages Reputational Harm

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 6 Authorities cited 11 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Lakeville Investments Limited

Plaintiff

Mat & Spencer Limited

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether there was a valid and binding contract between the parties for the delivery and completion of work as stipulated in a quotation within 59 working days.
  2. 2 Whether the Defendant breached the terms of the contract.
  3. 3 Whether the Defendant's actions occasioned loss of reputation and economic loss to the Plaintiff.

Ratio Decidendi

The court found that a valid and binding contract existed between the parties, supported by the quotation and partial performance. The Defendant breached the contract by failing to complete the subdivision and titling of plots within the stipulated 59 working days. However, the Plaintiff also breached the contract by failing to pay the full contract sum, contributing to delays. The court found cross-breach but held the Defendant primarily liable for breach of contract. The Plaintiff failed to prove a direct causal link between the Defendant's breach and alleged reputational or economic loss, as the evidence showed that offers to customers predated the contract and the Defendant was not...

Court Disposition

Suit partially succeeds; declaration of breach granted; nominal damages awarded; other claims denied; each party to bear own costs.

Orders

  • Declaration that the Defendant was in breach of its contract with the Plaintiff.
  • Plaintiff awarded nominal damages of UGX 1,000,000/=