[2023] UGCA 118

[2023] UGCA 118

The Court of Appeal found that the Ministry of Works and Transport did not waive its right to terminate the contract for non-completion, as there was no express or implied agreement or conduct amounting to waiver or acquiescence. The contract expressly treated time as a condition, and the appellant's repeated...

Source-derived case information.

Citation
[2023] UGCA 118
Parties
Appellant: M & B Engineers Ltd; Respondent: Uganda National Roads Authority; Respondent: Attorney General
Court
Court of Appeal of Uganda
Jurisdiction
Uganda
Case Number
Civil Appeal No. 316 of 2021
Procedural Posture
Civil Appeal / Final Judgment
Outcome
Appeal and cross-appeal dismissed. Each party to bear its own costs.
Judges
Kibeedi Mutangula, JA, Gashirabake, JA, Musoke, JA
Legal Topics
Breach of Contract, Termination of Contract, Liquidated Damages, Waiver and Acquiescence, Unjust Enrichment, Quantum Meruit
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Termination of Contract Liquidated Damages Waiver and Acquiescence Unjust Enrichment Quantum Meruit

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 19 Party arguments 2 Amounts and remedies 6
Sign in to unlock

Parties

M & B Engineers Ltd

Appellant

Uganda National Roads Authority

Respondent

Attorney General

Respondent

Procedural Posture

Civil Appeal / Final Judgment

  1. 1 Whether the respondent waived the agreed completion date and acquiesced to continued performance by the appellant.
  2. 2 Whether the termination of the contract was lawful and based on fundamental breach.
  3. 3 Whether the seizure of the appellant's materials and equipment was lawful under the contract.

Ratio Decidendi

The Court of Appeal found that the Ministry of Works and Transport did not waive its right to terminate the contract for non-completion, as there was no express or implied agreement or conduct amounting to waiver or acquiescence. The contract expressly treated time as a condition, and the appellant's repeated failure to complete works, coupled with substandard performance and abandonment of the site, constituted fundamental breach. The employer was entitled to terminate the contract and lawfully seize the appellant's materials and equipment under Clause 61 of the GCC. The appellant was not entitled to damages, lost earnings, or payment for seized goods, as the breaches were proved and the...

Court Disposition

Appeal and cross-appeal dismissed. Each party to bear its own costs.

Orders

  • The appeal is dismissed in its entirety.
  • The cross-appeal is dismissed in its entirety.