[2023] UGHC 273

[2023] UGHC 273

The court found that the contract's dispute resolution mechanism requires disputes to first be referred to an adjudicator, and only after an adjudicator's decision may arbitration be pursued. The contract does not contain a clear, direct arbitration clause for the present dispute, which concerns breach of contract...

Source-derived case information.

Citation
[2023] UGHC 273
Parties
Applicant: Mbarara University of Science and Technology; Respondent: Block Technical Services Limited
Court
High Court of Uganda
Jurisdiction
Uganda
Case Number
Miscellaneous Application 397 of 2022
Procedural Posture
Miscellaneous Application / Ruling
Outcome
application dismissed
Judges
Joyce Kavuma, J
Legal Topics
Arbitration Agreement Validity, Contractual Dispute Resolution, Preliminary Objection, Adjudicator Role
Source Language
en
Civil Procedure Alternative Dispute Resolution Arbitration Agreement Validity Contractual Dispute Resolution Preliminary Objection Adjudicator Role

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 8 Party arguments 2
Sign in to unlock

Parties

Mbarara University of Science and Technology

Applicant

Block Technical Services Limited

Respondent

Procedural Posture

Miscellaneous Application / Ruling

  1. 1 Whether there is an arbitration agreement between the parties and if so, whether the arbitration agreement is valid and enforceable against the parties.
  2. 2 What remedies are available to the parties.

Ratio Decidendi

The court found that the contract's dispute resolution mechanism requires disputes to first be referred to an adjudicator, and only after an adjudicator's decision may arbitration be pursued. The contract does not contain a clear, direct arbitration clause for the present dispute, which concerns breach of contract rather than a project manager's decision. The relevant clauses (GCC 33.1-34.4 and SCC) do not provide for immediate arbitration, and the court cannot enforce a vague or defective arbitration clause. Therefore, the application to refer the dispute to arbitration was dismissed. However, the court noted that if both parties agree, they may pursue arbitration or other alternative...

Court Disposition

application dismissed

Orders

  • Should the parties so decide, the matter may be referred for arbitration to the International Center for Arbitration and Mediation (ICAMEK) in accordance with clauses 34.1-34.4 GCC to be concluded within 90 days of such decision.
  • The costs of the suit shall abide the outcome of the Arbitration.