[2024] UGPPDPAAT 38

[2024] UGPPDPAAT 38

The Tribunal held that it lacked jurisdiction to entertain the application because the Applicant failed to adduce cogent and reasonable evidence of conflict of interest or partiality by the Respondent's Accounting Officer. Mere allegations and dissatisfaction with the procurement process, including the display of...

Source-derived case information.

Citation
[2024] UGPPDPAAT 38
Parties
Applicant: MBJ Technologies Limited; Respondent: Mbarara City Council
Court
Public Procurement and Disposal of Public Assets Appeals Tribunal
Jurisdiction
Uganda
Case Number
Application 37 of 2024
Procedural Posture
Procurement Review Application / Final Tribunal Decision
Outcome
application_struck_out
Judges
Gimara SC, Chairperson, Nerima, Panel Member, Kalumba, Kyarisiima, cyrus Titus Aomu, penal member
Legal Topics
Public Procurement Review, Bid Evaluation Challenge, Conflict of Interest, Display of Technical Scores, Eligibility of Bidders
Source Language
en
Administrative Law Commercial and Corporate Public Procurement Review Bid Evaluation Challenge Conflict of Interest Display of Technical Scores Eligibility of Bidders

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 24 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

MBJ Technologies Limited

Applicant

Mbarara City Council

Respondent

Procedural Posture

Procurement Review Application / Final Tribunal Decision

  1. 1 Whether the application before the Tribunal is competent.
  2. 2 Whether the Respondent erred in law by not displaying technical bid scores before opening financial proposals or omitting to avail the Applicant with technical scores before financial opening.
  3. 3 Whether Athwax Consultants Limited's bid was lawfully determined to be the best-evaluated bid by the Respondent.

Ratio Decidendi

The Tribunal held that it lacked jurisdiction to entertain the application because the Applicant failed to adduce cogent and reasonable evidence of conflict of interest or partiality by the Respondent's Accounting Officer. Mere allegations and dissatisfaction with the procurement process, including the display of technical scores and evaluation of Athwax Consultants Limited, did not meet the threshold for direct access to the Tribunal under Section 106(9) and 115(1)(c) of the Public Procurement and Disposal of Public Assets Act. The Tribunal emphasized that the burden of proof lies with the Applicant to demonstrate a real likelihood of bias or conflict of interest, which was not...

Court Disposition

application_struck_out

Orders

  • The application is struck out.
  • The Respondent may continue with the procurement to its logical conclusion.