[2023] UGCommC 94

[2023] UGCommC 94

The court found that the Plaintiff supplied goods worth UGX 51,191,000 to the Defendant under a Local Purchase Order, and the Defendant received and used the goods, including resale to a third party. The Defendant's argument that the Plaintiff was required to supply pre-fabricated painted angle bars was unsupported,...

Source-derived case information.

Citation
[2023] UGCommC 94
Parties
Plaintiff: Memer Engineering Supplies (U) Limited; Defendant: Divine Light Finance Ltd
Court
Commercial Court of Uganda
Jurisdiction
Uganda
Case Number
Civil Suit 762 of 2019
Procedural Posture
Civil Suit / Judgment
Outcome
Judgment for the Plaintiff.
Judges
Abinyo, J
Legal Topics
Breach of Contract, Sale of Goods, Damages Assessment, Interest Awards, Burden of Proof
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Sale of Goods Damages Assessment Interest Awards Burden of Proof

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 6 Authorities cited 15 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

Memer Engineering Supplies (U) Limited

Plaintiff

Divine Light Finance Ltd

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether there was breach of contract, and if so, by whom.
  2. 2 What remedies are available to the parties.

Ratio Decidendi

The court found that the Plaintiff supplied goods worth UGX 51,191,000 to the Defendant under a Local Purchase Order, and the Defendant received and used the goods, including resale to a third party. The Defendant's argument that the Plaintiff was required to supply pre-fabricated painted angle bars was unsupported, as there was no evidence that the Plaintiff was privy to the sub-contract between the Defendant and the third party. The Plaintiff's evidence of supply and delivery was uncontroverted. The Defendant's failure to pay for the goods supplied constituted a breach of contract. The Plaintiff discharged the burden of proof for special damages, and the Defendant was held liable for...

Court Disposition

Judgment for the Plaintiff.

Orders

  • Special damages of UGX 51,191,000 awarded to the Plaintiff.
  • General damages of UGX 25,000,000 awarded to the Plaintiff.