[2020] UGEDT 3

[2020] UGEDT 3

The tribunal found that the applicant failed to prove that a complaint was lodged with the Electricity Regulatory Authority (ERA) prior to the disconnection of his electricity supply, as required by Regulation 15.6.1(a) of the Electricity (Primary Grid Code) Regulations. The applicant did not attach any evidence of...

Source-derived case information.

Citation
[2020] UGEDT 3
Parties
Applicant: Michael Mugambe Kibirango; Respondent: Umeme Ltd
Court
Electricity Disputes Tribunal
Jurisdiction
Uganda
Case Number
MISCELLENOUS APPLICANT EDT 1 of 2020
Procedural Posture
Miscellaneous Application / Interlocutory Application for Interim Orders Pending Main Complaint
Outcome
application dismissed with costs
Judges
Charles Okoth Owor - Chairperson Electricity Disputes Tribunal, Anaclet Turyakira, - Vice Chair Person Electricty Disputes Tribunal, Dr. Terry Kahuma - Member Electricty Disputes Tribunal
Legal Topics
Interim Injunctions, Electricity Supply Disputes, Burden of Proof, Regulatory Compliance
Source Language
en
Civil Procedure Commercial and Corporate Interim Injunctions Electricity Supply Disputes Burden of Proof Regulatory Compliance

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 3 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Michael Mugambe Kibirango

Applicant

Umeme Ltd

Respondent

Procedural Posture

Miscellaneous Application / Interlocutory Application for Interim Orders Pending Main Complaint

  1. 1 Whether the applicant is entitled to an interim order for reconnection of electricity pending determination of the main complaint.
  2. 2 Whether the applicant proved that a complaint was lodged with ERA prior to disconnection, as required by the relevant regulations.
  3. 3 Whether the respondent's disconnection of power was lawful and in accordance with the Electricity (Primary Grid Code) Regulations.

Ratio Decidendi

The tribunal found that the applicant failed to prove that a complaint was lodged with the Electricity Regulatory Authority (ERA) prior to the disconnection of his electricity supply, as required by Regulation 15.6.1(a) of the Electricity (Primary Grid Code) Regulations. The applicant did not attach any evidence of a complaint to ERA at the relevant time, and the only indication of such a complaint was raised after the respondent's affidavit in reply. The tribunal distinguished the cases cited by the applicant, noting that in those cases, evidence of a pending complaint existed or there were exceptional circumstances. The tribunal emphasized that the grant of interim orders for...

Court Disposition

application dismissed with costs

Orders

  • The application for interim reconnection of electricity is dismissed.
  • The applicant shall pay the costs of this application.