[2005] UGHCCD 27

[2005] UGHCCD 27

The court found that a valid contract existed between the parties for the supply, installation, and servicing of fire-fighting equipment, and that the plaintiff paid the contract sum in full except for a minor shortfall. The defendant failed to deliver all contracted items and did not perform installation,...

Source-derived case information.

Citation
[2005] UGHCCD 27
Parties
Plaintiff: African Textile Mill Ltd; Defendant: Techno Fire Appliances Ltd
Court
HC: Civil Division (Uganda)
Jurisdiction
Uganda
Case Number
CIVIL SUIT NO. 07 OF 1998
Procedural Posture
Civil Suit / Judgment
Outcome
judgment_for_plaintiff
Judges
Rugadya, J
Legal Topics
Breach of Contract, Sale of Goods, Damages for Non Delivery, Contractual Remedies
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Sale of Goods Damages for Non Delivery Contractual Remedies

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 7 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

African Textile Mill Ltd

Plaintiff

Techno Fire Appliances Ltd

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether the plaintiff and defendant entered into a contract to supply, install and service fire-fighting equipment worth shs. 44,050,350/=.
  2. 2 Whether the defendant was paid the contract sum.
  3. 3 Whether the defendant breached the contract.

Ratio Decidendi

The court found that a valid contract existed between the parties for the supply, installation, and servicing of fire-fighting equipment, and that the plaintiff paid the contract sum in full except for a minor shortfall. The defendant failed to deliver all contracted items and did not perform installation, servicing, or training as required. The defendant's argument regarding labour unrest was rejected, as the unrest occurred after the contractual completion date and no evidence was adduced to show alteration of the completion date. The plaintiff proved on a balance of probabilities that the defendant breached the contract. The plaintiff is entitled to recover the value of undelivered...

Court Disposition

judgment_for_plaintiff

Orders

  • The plaintiff shall recover the sum of shs. 12,372,322/-.
  • The plaintiff shall be paid general damages for breach of contract of shs. 500,000/-.