[2015] UGPPDPAAT 3

[2015] UGPPDPAAT 3

The Tribunal found that the services sought in the new procurement—design review and supervision—were not a continuation of the applicant's previous consultancy, but rather constituted further services. The previous contract had been fully executed, with the applicant submitting a final report and the assignment...

Source-derived case information.

Citation
[2015] UGPPDPAAT 3
Parties
Applicant: M/S Arch Designs Ltd.; Respondent: Public Procurement and Disposal of Public Assets Authority
Court
Public Procurement and Disposal of Public Assets Appeals Tribunal
Jurisdiction
Uganda
Case Number
Application 10 of 2015
Procedural Posture
Administrative Review / Decision on Application for Review of Procurement Authority Decision
Outcome
application dismissed
Judges
Olive Zaare Otete - Chairperson, Moses Jurua Adriko SC - Panel Member, David Kabateraine - Panel Member, Joel Kateregga - Panel Member
Legal Topics
Public Procurement, Conflict of Interest, Consultancy Contracts, Tendering Process
Source Language
en
Administrative Law Commercial and Corporate Public Procurement Conflict of Interest Consultancy Contracts Tendering Process

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 1 Party arguments 2
Sign in to unlock

Parties

M/S Arch Designs Ltd.

Applicant

Public Procurement and Disposal of Public Assets Authority

Respondent

Procedural Posture

Administrative Review / Decision on Application for Review of Procurement Authority Decision

  1. 1 Whether the consultancy services sought in the new procurement process were a continuation of services or further services within the meaning of Clause 37.2 of the previous contract.
  2. 2 Whether the applicant was barred from participating in the new tender due to conflict of interest arising from prior involvement.

Ratio Decidendi

The Tribunal found that the services sought in the new procurement—design review and supervision—were not a continuation of the applicant's previous consultancy, but rather constituted further services. The previous contract had been fully executed, with the applicant submitting a final report and the assignment concluded. The Tribunal reasoned that if the Entity had intended a continuation of services, it would have structured the contract accordingly, possibly in two phases. The new procurement specifically called for review of designs already submitted by the applicant, making it unreasonable to expect an unbiased review from the same party. Clause 37.2 of the previous contract...

Court Disposition

application dismissed

Orders

  • The application is dismissed.
  • Each party shall bear its own legal costs.