[2023] UGHCLD 16

[2023] UGHCLD 16

The court found that the Plaintiff had fully performed his contractual obligations by paying the agreed purchase price for the suit land, but the Defendants failed to deliver the certificate of title or possession of the land as required under the sale agreement. Despite repeated reminders and promises, including an...

Source-derived case information.

Citation
[2023] UGHCLD 16
Parties
Plaintiff: Ben Mukiise; Defendant: Akright Projects Limited; Defendant: Anatoli Kamugisha
Court
HC: Land Division (Uganda)
Jurisdiction
Uganda
Case Number
Civil Suit No. 703 of 2017
Procedural Posture
Civil Suit / Judgment
Outcome
judgment for the plaintiff
Judges
Kazaarwe, J
Legal Topics
Breach of Contract, Sale of Land, Remedies for Breach, Specific Performance, Damages, Contractual Obligations
Source Language
en
Land and Property Civil Procedure Breach of Contract Sale of Land Remedies for Breach Specific Performance Damages Contractual Obligations

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 3 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Ben Mukiise

Plaintiff

Akright Projects Limited

Defendant

Anatoli Kamugisha

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether the 1st Defendant is in breach of the sale agreement dated 10th April 2012.
  2. 2 What remedies are available to the Plaintiff.

Ratio Decidendi

The court found that the Plaintiff had fully performed his contractual obligations by paying the agreed purchase price for the suit land, but the Defendants failed to deliver the certificate of title or possession of the land as required under the sale agreement. Despite repeated reminders and promises, including an unfulfilled offer of alternative land, the Defendants did not provide any value for the Plaintiff's payment. The court held that this constituted a clear breach of contract under the Contracts Act 2010. As a result, the Plaintiff was entitled to recover the purchase price, general damages for inconvenience, interest, and costs. The court declined to order specific performance...

Court Disposition

judgment for the plaintiff

Orders

  • The 1st Defendant is declared in breach of the sale agreement dated 10th April 2012.
  • The Plaintiff is awarded recovery of UGX 36,000,000 as money had and received for no consideration out of the agreement for sale of land.