[1950] EACA 117

[1950] EACA 117

The Court held that the injury for which special damages were claimed must have occurred no later than the date of completion of the contractor's work, and therefore the claim was barred by limitation. The damages sought were for the cost of repairing errors made by the contractor, which could not have arisen from...

Source-derived case information.

Citation
[1950] EACA 117
Parties
Appellant: Municipal Board of Mombasa; Respondent: A. G. W. Ogilvie
Court
East African Court of Appeal
Jurisdiction
Uganda
Case Number
Civil Appeal No. 59 of 1955
Procedural Posture
Civil Appeal / Appeal From Supreme Court Preliminary Limitation Ruling
Outcome
appeal_dismissed
Judges
Bacon, JA, Briggs, JA, Worley, P
Legal Topics
Contractual Limitation Periods, Architect Liability, Pleading Requirements, Special and General Damages
Source Language
en
Commercial and Corporate Civil Procedure Contractual Limitation Periods Architect Liability Pleading Requirements Special and General Damages

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 2 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Municipal Board of Mombasa

Appellant

A. G. W. Ogilvie

Respondent

Procedural Posture

Civil Appeal / Appeal From Supreme Court Preliminary Limitation Ruling

  1. 1 Whether the claim for special damages for defects in the buildings is barred by limitation under the contract.
  2. 2 Whether the issue of final certificates by the architect constitutes a separate breach of contract giving rise to a distinct cause of action within the limitation period.
  3. 3 Whether the pleadings support a claim for general damages arising from the issue of final certificates.

Ratio Decidendi

The Court held that the injury for which special damages were claimed must have occurred no later than the date of completion of the contractor's work, and therefore the claim was barred by limitation. The damages sought were for the cost of repairing errors made by the contractor, which could not have arisen from any breach of contract committed after the work was completed. The issue of the final certificates by the architect, even if considered a separate breach, could not logically or legally be the source of the damages claimed. Furthermore, the pleadings did not contain any prayer for general damages, and the common form claim for 'further or other relief' was not wide enough to...

Court Disposition

appeal_dismissed

Orders

  • Appeal dismissed with costs to the respondent, except costs arising from the filing of the notice of cross-appeal, which are disallowed.