[2017] UGHCCD 206

[2017] UGHCCD 206

The court found that although there are serious issues to be tried regarding ownership of the suit land, the status quo had already been substantially altered due to the applicants' failure to extend the interim order. The rock had been quarried and the land changed, making it impossible to restore the original...

Source-derived case information.

Citation
[2017] UGHCCD 206
Parties
Applicant: Herbert Mutekanga; Applicant: Ntende Fidah; Respondent: Basalirwa Harriet; Respondent: Chongquing International Construction Company
Court
HC: Civil Division (Uganda)
Jurisdiction
Uganda
Case Number
MISC. APPLICATION No. 411 of 2016
Procedural Posture
Miscellaneous Application / Ruling on Application for Temporary Injunction
Outcome
application dismissed
Judges
Elubu, J
Legal Topics
Temporary Injunctions, Status Quo Preservation, Irreparable Damage, Balance of Convenience
Source Language
en
Civil Procedure Land and Property Temporary Injunctions Status Quo Preservation Irreparable Damage Balance of Convenience

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 3 Party arguments 2
Sign in to unlock

Parties

Herbert Mutekanga

Applicant

Ntende Fidah

Applicant

Basalirwa Harriet

Respondent

Chongquing International Construction Company

Respondent

Procedural Posture

Miscellaneous Application / Ruling on Application for Temporary Injunction

  1. 1 Whether a temporary injunction should issue to restrain the respondents from interfering with the suit land until disposal of the main suit.
  2. 2 Whether the applicants will suffer irreparable damage if the injunction is not granted.
  3. 3 Where the balance of convenience lies between the parties.

Ratio Decidendi

The court found that although there are serious issues to be tried regarding ownership of the suit land, the status quo had already been substantially altered due to the applicants' failure to extend the interim order. The rock had been quarried and the land changed, making it impossible to restore the original state. The balance of convenience favored the respondents, who were carrying out public road works under contractual obligations. The court held that any loss suffered by the applicants could be compensated by damages, and there was no risk of irreparable harm. Consequently, the application for a temporary injunction lacked merit and was dismissed.

Court Disposition

application dismissed

Orders

  • The application for a temporary injunction is dismissed.
  • Costs in the cause.