[2004] UGHC 61

[2004] UGHC 61

The plaintiff proved, through documentary and oral evidence, that it supplied petroleum products to the defendant under a dealership agreement and that the defendant failed to pay for two specific invoices. The defendant's absence and failure to adduce evidence meant the plaintiff's case was uncontroverted. The...

Source-derived case information.

Citation
[2004] UGHC 61
Parties
Plaintiff: Petro (U) Ltd; Defendant: Sailesh Kumar Mambhai Patel
Court
High Court of Uganda
Jurisdiction
Uganda
Case Number
HCCS No. 696 of 2002
Procedural Posture
Civil Suit / Judgment
Outcome
judgment_for_plaintiff
Legal Topics
Breach of Contract, Supply of Goods, Recovery of Debt, Counterclaim Dismissal
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Supply of Goods Recovery of Debt Counterclaim Dismissal

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 2 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Petro (U) Ltd

Plaintiff

Sailesh Kumar Mambhai Patel

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether the money claimed by the plaintiff is due and outstanding.
  2. 2 What remedies are available to the parties.

Ratio Decidendi

The plaintiff proved, through documentary and oral evidence, that it supplied petroleum products to the defendant under a dealership agreement and that the defendant failed to pay for two specific invoices. The defendant's absence and failure to adduce evidence meant the plaintiff's case was uncontroverted. The court found the claim valid and awarded the sum claimed, general damages for breach of contract, and interest. The defendant's counterclaim was dismissed for want of prosecution. The court exercised discretion to reduce the proposed general damages from Shs. 5 million to Shs. 3 million, considering the circumstances. Interest was awarded at 20% per annum on the liquidated sum and...

Court Disposition

judgment_for_plaintiff

Orders

  • The defendant shall pay the plaintiff Shs. 35,057,429.
  • Interest on the above sum at 20% per annum from date of filing until payment in full.