[2025] UGCommC 136

[2025] UGCommC 136

The court found that the dispute over retention monies and the issuance of the completion certificate arises from a determination made by the project manager, as evidenced by the letter from the Permanent Secretary, Ministry of Energy and Mineral Development. This determination falls squarely within the scope of the...

Source-derived case information.

Citation
[2025] UGCommC 136
Parties
Plaintiff: Planbuild Technical Services Limited; Defendant: Attorney General
Court
Commercial Court of Uganda
Jurisdiction
Uganda
Case Number
Civil Suit No. 1273 of 2023
Procedural Posture
Civil Suit / Ruling on Preliminary Objection (jurisdiction/arbitration Clause)
Outcome
suit stayed; parties referred to arbitration
Judges
Susan Odongo, J
Legal Topics
Arbitration Clause Scope, Contractual Dispute Resolution, Retention Money Claim, Construction Contracts
Source Language
en
Commercial and Corporate Civil Procedure Arbitration Clause Scope Contractual Dispute Resolution Retention Money Claim Construction Contracts

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 8 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Planbuild Technical Services Limited

Plaintiff

Attorney General

Defendant

Procedural Posture

Civil Suit / Ruling on Preliminary Objection (jurisdiction/arbitration Clause)

  1. 1 Whether the claim in this suit falls within the arbitration clause under the contract and is thus governed by the Arbitration and Conciliation Act.
  2. 2 Whether the dispute regarding retention monies and completion certificate is subject to arbitration as per the contract.

Ratio Decidendi

The court found that the dispute over retention monies and the issuance of the completion certificate arises from a determination made by the project manager, as evidenced by the letter from the Permanent Secretary, Ministry of Energy and Mineral Development. This determination falls squarely within the scope of the arbitration clause set out in GCC Clauses 24 to 25 of the contract. The arbitration clause is valid, operative, and capable of being performed with respect to the present dispute. The court is mandated by Section 5 of the Arbitration and Conciliation Act to refer such matters to arbitration unless exceptions apply, which are not present in this case. Therefore, the suit is...

Court Disposition

suit stayed; parties referred to arbitration

Orders

  • The suit is stayed.
  • The parties are directed to resolve the dispute by arbitration in accordance with the dispute settlement clause under the Agreement.