[2015] UGPPDPAAT 6

[2015] UGPPDPAAT 6

The Tribunal found that the Respondent's Accounting Officer executed a contract with the best evaluated bidder during the administrative review period, in direct contravention of sections 90(7)(a) and (b) of the PPDA Act, 2003. The administrative review period is sequential and continuous, barring any contract...

Source-derived case information.

Citation
[2015] UGPPDPAAT 6
Parties
Applicant: Public Procurement and Disposal of Assets Authority (PPDA); Respondent: Mbarara Municipal Council
Court
Public Procurement and Disposal of Public Assets Appeals Tribunal
Jurisdiction
Uganda
Case Number
Reference 1 of 2015
Procedural Posture
Administrative Review Reference / Final Decision
Outcome
reference allowed; declaration of serious breach; costs awarded to applicant
Judges
Moses Jurua Adriko SC - Panel Member, David Kabateraine - Panel Member, Abraham Nkata - Member, Joel Kateregga - Panel Member
Legal Topics
Public Procurement Breach, Administrative Review Process, Disciplinary Action, Contract Execution During Review
Source Language
en
Administrative Law Civil Procedure Public Procurement Breach Administrative Review Process Disciplinary Action Contract Execution During Review

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 4 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Public Procurement and Disposal of Assets Authority (PPDA)

Applicant

Mbarara Municipal Council

Respondent

Procedural Posture

Administrative Review Reference / Final Decision

  1. 1 Whether the Accounting Officer of the Respondent entered into a contract with M/s Mbarara United Taxi Operators Cooperative Society Ltd during the period of administrative review.
  2. 2 Whether the actions of the Accounting Officer amounted to a serious breach of the Public Procurement and Disposal of Public Assets Act, 2003.
  3. 3 What remedies are available for a serious breach of the Act.

Ratio Decidendi

The Tribunal found that the Respondent's Accounting Officer executed a contract with the best evaluated bidder during the administrative review period, in direct contravention of sections 90(7)(a) and (b) of the PPDA Act, 2003. The administrative review period is sequential and continuous, barring any contract execution until all review processes are exhausted. The Respondent's actions frustrated both the Authority's statutory mandate and the aggrieved bidder's right to review, constituting a flagrant violation of mandatory statutory provisions. The Tribunal held that such conduct amounts to a serious breach of the Act, warranting a formal declaration and disciplinary recommendation....

Court Disposition

reference allowed; declaration of serious breach; costs awarded to applicant

Orders

  • The Tribunal declares that the decision of Mbarara Municipal Council to execute a contract in respect of procurement reference number Mbar761/Srvcs/00008 during the Administrative Review period amounted to a serious breach of the Act.
  • The Respondent is ordered to pay costs of Uganda shillings three million only to the Applicant.