[2024] UGPPDPAAT 22

[2024] UGPPDPAAT 22

The Tribunal found that the applicant had locus standi to bring a direct application due to a reasonable belief that the respondent's Accounting Officer could not impartially handle the complaint, given unresolved issues from a previous contract. The evaluation process was fundamentally flawed: the impugned...

Source-derived case information.

Citation
[2024] UGPPDPAAT 22
Parties
Applicant: Rhino Engineering Works Limited; Respondent: Otuke District Local Government
Court
Public Procurement and Disposal of Public Assets Appeals Tribunal
Jurisdiction
Uganda
Case Number
Application 24 of 2024
Procedural Posture
Administrative Review Application / Final Tribunal Decision
Outcome
application_allowed
Judges
Nerima, Panel Member, Isanga, Nuwagira, Kalumba, Kyarisiima
Legal Topics
Public Procurement Review, Evaluation Committee Appointment, Conflict of Interest, Bid Disqualification, Due Diligence Requirements
Source Language
en
Administrative Law Civil Procedure Public Procurement Review Evaluation Committee Appointment Conflict of Interest Bid Disqualification Due Diligence Requirements

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 8 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Rhino Engineering Works Limited

Applicant

Otuke District Local Government

Respondent

Procedural Posture

Administrative Review Application / Final Tribunal Decision

  1. 1 Whether the applicant has locus standi before the Tribunal.
  2. 2 Whether the evaluation of the bids in the impugned procurement was conducted lawfully.
  3. 3 What remedies are available to the parties.

Ratio Decidendi

The Tribunal found that the applicant had locus standi to bring a direct application due to a reasonable belief that the respondent's Accounting Officer could not impartially handle the complaint, given unresolved issues from a previous contract. The evaluation process was fundamentally flawed: the impugned Evaluation Committee was not properly nominated or approved, and the use of Alebtong District's Contracts Committee lacked a written agreement. The respondent disqualified the applicant's bid for reasons extraneous to the stated evaluation criteria, violating statutory requirements that evaluation and post qualification must strictly adhere to the bidding documents. The Tribunal held...

Court Disposition

application_allowed

Orders

  • The application is allowed.
  • The award of the contract to UNIFIED INVESTMENT COMPANY LTD is set aside.