[2023] UGPPDPAAT 27

[2023] UGPPDPAAT 27

The Tribunal found that Green Power International Limited and Green Power International referred to the same legal entity, and the omission of 'Limited' was a non-fatal misnomer. However, the bid of Green Power International Limited was not substantially compliant with the requirements of the bidding document, as it...

Source-derived case information.

Citation
[2023] UGPPDPAAT 27
Parties
Applicant: Samanga Solutions Ltd; Respondent: Uganda National Roads Authority
Court
Public Procurement and Disposal of Public Assets Appeals Tribunal
Jurisdiction
Uganda
Case Number
Application 25 of 2023
Procedural Posture
Application for Review / Final Determination by Tribunal
Outcome
application allowed; award set aside; re-evaluation ordered
Judges
Gimara SC, Chairperson, Nerima, Panel Member, Isanga, Nuwagira, Kyarisiima, Kayemba
Legal Topics
Public Procurement, Bid Evaluation, Contract Award Challenge, Procurement Regulations
Source Language
en
Administrative Law Commercial and Corporate Public Procurement Bid Evaluation Contract Award Challenge Procurement Regulations

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 10 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Samanga Solutions Ltd

Applicant

Uganda National Roads Authority

Respondent

Procedural Posture

Application for Review / Final Determination by Tribunal

  1. 1 Whether Green Power International Limited is different from Green Power International.
  2. 2 Whether the bid of Green Power International Limited was substantially compliant with the requirements of the bidding document.
  3. 3 Whether the Respondent erred when it requested Green Power International Ltd to submit a copy of a certificate of completion as a clarification.

Ratio Decidendi

The Tribunal found that Green Power International Limited and Green Power International referred to the same legal entity, and the omission of 'Limited' was a non-fatal misnomer. However, the bid of Green Power International Limited was not substantially compliant with the requirements of the bidding document, as it failed to demonstrate the required general experience over five years with activity in at least nine months of each year, and did not provide all necessary documentation for specific experience. The Tribunal held that the respondent erred in seeking clarification for a material deviation, as the missing completion certificate was a commercial criterion, not a mere eligibility...

Court Disposition

application allowed; award set aside; re-evaluation ordered

Orders

  • The application is allowed.
  • The award of the contract to Green Power International Ltd is set aside.