[2000] UGCA 46

[2000] UGCA 46

The Court of Appeal held that the contract between the parties was negotiated and performed in Uganda Shillings, as evidenced by the delivery notes and payment records. There was no agreement to peg the contract price to the US Dollar, and the claim for special damages arising from currency fluctuation was too...

Source-derived case information.

Citation
[2000] UGCA 46
Parties
Appellant: Star Supermarket (U) Ltd; Respondent: Attorney General
Court
Court of Appeal of Uganda
Jurisdiction
Uganda
Case Number
CIVIL APPEAL NO. 34 OF 2000
Procedural Posture
Civil Appeal / Judgment
Outcome
appeal allowed in part and dismissed in part
Judges
Okello, JA, Berko, JA, Twinomujuni, JA
Legal Topics
Contract for Supply of Goods, Interest on Decretal Sum, Special Damages, Currency Fluctuation, Remoteness of Damage
Source Language
en
Commercial and Corporate Civil Procedure Contract for Supply of Goods Interest on Decretal Sum Special Damages Currency Fluctuation Remoteness of Damage

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 2 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Star Supermarket (U) Ltd

Appellant

Attorney General

Respondent

Procedural Posture

Civil Appeal / Judgment

  1. 1 Whether the appellant is entitled to special damages arising from currency fluctuation between US Dollars and Uganda Shillings.
  2. 2 Whether the trial judge erred in awarding 6% interest instead of the claimed 36% on the decretal sum.
  3. 3 Whether the contract was performed in Uganda Shillings or US Dollars.

Ratio Decidendi

The Court of Appeal held that the contract between the parties was negotiated and performed in Uganda Shillings, as evidenced by the delivery notes and payment records. There was no agreement to peg the contract price to the US Dollar, and the claim for special damages arising from currency fluctuation was too remote and not contemplated by the parties at the time of contracting. The trial judge was correct to reject the claim for special damages. Regarding interest, the court found that the transaction was commercial in nature and warranted a higher interest rate than the 6% awarded by the trial judge. The court exercised its discretion to increase the interest rate to 25% per annum from...

Court Disposition

appeal allowed in part and dismissed in part

Orders

  • Special damages claim is rejected.
  • Interest rate on the decretal sum is set at 25% per annum from 19th June 1998 until payment in full.