[2021] UGCommC 137

[2021] UGCommC 137

The court found that although the plaintiff exceeded the contractual completion period, time was not of the essence and the defendant waived its right to enforce liquidated damages by permitting continued work without setting a new deadline. The plaintiff achieved substantial and practical completion, entitling it...

Source-derived case information.

Citation
[2021] UGCommC 137
Parties
Plaintiff: Stone Crushing (U) Limited; Defendant: Roko Construction Limited
Court
Commercial Court of Uganda
Jurisdiction
Uganda
Case Number
Civil Suit 665 of 2017
Procedural Posture
Civil Suit / Judgment
Outcome
Judgment for the plaintiff; defendant's counterclaim dismissed.
Judges
Stephen Mubiru, J
Legal Topics
Construction Contracts, Breach of Contract, Damages Assessment, Subcontractor Rights, Liquidated Damages, Mitigation of Loss
Source Language
en
Commercial and Corporate Civil Procedure Construction Contracts Breach of Contract Damages Assessment Subcontractor Rights Liquidated Damages Mitigation of Loss

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 18 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Stone Crushing (U) Limited

Plaintiff

Roko Construction Limited

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether the sub-contract was completed within the required time and to the required standard.
  2. 2 Whether the defendant breached the sub-contract for the works on the altar and the bridge.
  3. 3 Whether the plaintiff is entitled to the sum of shs. 130,667,517/= as claimed.

Ratio Decidendi

The court found that although the plaintiff exceeded the contractual completion period, time was not of the essence and the defendant waived its right to enforce liquidated damages by permitting continued work without setting a new deadline. The plaintiff achieved substantial and practical completion, entitling it to the outstanding contract balance. The defendant's counterclaim for rectification costs failed due to lack of proof and evidence showed the plaintiff performed the rectification. The claim for materials purchased for the bridge was denied as the plaintiff failed to obtain approval for shop drawings and did not deliver the materials to site, making them its property. The claim...

Court Disposition

Judgment for the plaintiff; defendant's counterclaim dismissed.

Orders

  • Plaintiff awarded shs. 57,870,627/= as outstanding balance.
  • Plaintiff awarded shs. 10,500,000/= as general damages for breach of contract.