The Tribunal found that the application was competently filed within the statutory timeframe following the publication of the Best Evaluated Bidder Notice and subsequent administrative review decision. The Accounting Officer's delay in communicating the decision was a breach of statutory requirements, but the...

Source-derived case information.

Citation
[2022] UGPPDPAAT 6
Parties
Applicant: Technology Associates Limited in Consortium with Comviva Technologies Limited; Respondent: Post Bank Uganda Limited
Court
Public Procurement and Disposal of Public Assets Appeals Tribunal
Jurisdiction
Uganda
Case Number
Application No. 6 of 2022
Procedural Posture
Administrative Review Application / Final Decision
Outcome
application dismissed
Judges
Nerima, Panel Member, Gimara SC, Chairperson, Isanga, Ag. Chairperson, Kakira, Kyarisiima, Kalumba, Asiimwe
Legal Topics
Public Procurement Review, Bid Evaluation Criteria, Administrative Timelines, Contract Award Process
Source Language
en
Administrative Law Commercial and Corporate Public Procurement Review Bid Evaluation Criteria Administrative Timelines Contract Award Process

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 12 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Technology Associates Limited in Consortium with Comviva Technologies Limited

Applicant

Post Bank Uganda Limited

Respondent

Procedural Posture

Administrative Review Application / Final Decision

  1. 1 Whether the Accounting Officer erred in law by not communicating the administrative review decision within the prescribed statutory timeframe.
  2. 2 Whether the Respondent Entity erred in law by not disqualifying the Best Evaluated Bidder at the post qualification stage due to lack of experience in supply, installation and commissioning of an e-wallet solution.
  3. 3 Whether the Respondent Entity erred in law by not providing evaluation criteria for experience and qualifications of key personnel in the bidding document and by not appropriately evaluating the key personnel of the Best Evaluated Bidder.

Ratio Decidendi

The Tribunal found that the application was competently filed within the statutory timeframe following the publication of the Best Evaluated Bidder Notice and subsequent administrative review decision. The Accounting Officer's delay in communicating the decision was a breach of statutory requirements, but the Tribunal had jurisdiction to hear the application. On substantive grounds, the Tribunal held that the evaluation and post qualification of the Best Evaluated Bidder were conducted in accordance with the criteria stated in the bidding document, and there was no evidence of deviation or unlawful modification. Complaints regarding the bidding document's sufficiency and alleged unlawful...

Court Disposition

application dismissed

Orders

  • The application is dismissed.
  • The procurement may proceed to its logical conclusion.