[2023] UGCommC 210

[2023] UGCommC 210

The court found that the Defendants breached the finance facility agreements by failing to repay the loan within the agreed period. Although the Plaintiff did not strictly comply with the 45-day notice requirement under Section 19(2) of the Mortgage Act, the sale of the mortgaged property occurred several months...

Source-derived case information.

Citation
[2023] UGCommC 210
Parties
Plaintiff: United Bank of Africa (U) Limited; Defendant: Mukafra Contractors Ltd; Defendant: Aliganyira Francis; Defendant: Bakigunja Christine
Court
Commercial Court of Uganda
Jurisdiction
Uganda
Case Number
Civil Suit 902 of 2016
Procedural Posture
Civil Suit / Judgment
Outcome
Plaintiff's claim succeeds in part; counterclaim dismissed.
Judges
Anna B. Mugenyi, J
Legal Topics
Loan Default, Mortgage Foreclosure, Valuation of Security, Remedies for Breach of Contract
Source Language
en
Banking and Finance Land and Property Loan Default Mortgage Foreclosure Valuation of Security Remedies for Breach of Contract

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 7 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

United Bank of Africa (U) Limited

Plaintiff

Mukafra Contractors Ltd

Defendant

Aliganyira Francis

Defendant

Bakigunja Christine

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether the Defendants breached the finance facility agreements executed with the Plaintiff.
  2. 2 Whether the foreclosure and sale of the mortgaged property was lawful.
  3. 3 Whether the Plaintiff is entitled to the remedies sought.

Ratio Decidendi

The court found that the Defendants breached the finance facility agreements by failing to repay the loan within the agreed period. Although the Plaintiff did not strictly comply with the 45-day notice requirement under Section 19(2) of the Mortgage Act, the sale of the mortgaged property occurred several months after the notices, and the Defendants had not remedied the default. The court held that the Plaintiff substantially complied with the statutory requirements for foreclosure and sale, including proper advertisement and valuation within the required period. The sale process, though involving payment by instalments contrary to Regulation 14, was not rendered unlawful by this...

Court Disposition

Plaintiff's claim succeeds in part; counterclaim dismissed.

Orders

  • Defendants to pay the Plaintiff UGX 153,967,568.92.
  • Interest at 31% per annum on UGX 153,967,568.92 from the date of default until payment in full.