[2019] UGHCCD 245

[2019] UGHCCD 245

The appellate court found that the memorandum of understanding only permitted the respondent to use the suit premises as an easement for access, not for parking or other uses. The appellant's management of the property, including erection of signposts, did not constitute a restriction of the respondent's easement or...

Source-derived case information.

Citation
[2019] UGHCCD 245
Parties
Appellant: Vision Impex Limited; Respondent: Gurushan Singh Ghatore
Court
HC: Civil Division (Uganda)
Jurisdiction
Uganda
Case Number
CIVIL APPEAL NO. 155 OF 2016
Procedural Posture
Civil Appeal / Judgment
Outcome
appeal allowed; trial court judgment and orders set aside; counterclaim succeeds
Judges
Mugambe, J
Legal Topics
Easement Rights, Breach of Memorandum of Understanding, Quiet Enjoyment, General Damages, Injunctions, Counterclaim Procedure
Source Language
en
Land and Property Civil Procedure Easement Rights Breach of Memorandum of Understanding Quiet Enjoyment General Damages Injunctions Counterclaim Procedure

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 2 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Vision Impex Limited

Appellant

Gurushan Singh Ghatore

Respondent

Procedural Posture

Civil Appeal / Judgment

  1. 1 Whether the appellant restricted the respondent's easement or common property rights.
  2. 2 Whether the appellant infringed the respondent's right to quiet enjoyment.
  3. 3 Whether the permanent injunctions issued against the appellant were justified.

Ratio Decidendi

The appellate court found that the memorandum of understanding only permitted the respondent to use the suit premises as an easement for access, not for parking or other uses. The appellant's management of the property, including erection of signposts, did not constitute a restriction of the respondent's easement or an infringement of quiet enjoyment. The respondent failed to contribute to maintenance as required by the MOU, amounting to a breach. The trial magistrate erred in issuing injunctions against the appellant and awarding damages to the respondent. The counterclaim by the appellant for breach of the MOU was upheld, and the appellant was entitled to general damages and costs.

Court Disposition

appeal allowed; trial court judgment and orders set aside; counterclaim succeeds

Orders

  • Appellant awarded general damages of Ug. Shs. 30,000,000.
  • Appellant awarded costs of the appeal and costs in the lower court.